Port Authority’s Saw Mill Run Boulevard Bridge, which closed Feb. 4 after one end shifted out of place, is expected reopen to buses Saturday.
The authority is waiting for final tests of light rail tracks embedded in the bridge surface before the structure is reopened. Buses will resume using the structure as soon as the testing is done, but light rail likely won’t use it until the end of the month because of track work near the Fallowfield Station, the agency said in a news release Friday.
The authority closed the bridge, which is part of the South Busway, after a worker noticed part of it was several inches out of place. An inspection and engineering review determined the bridge moved because water that had entered a concrete support froze and expanded.
Crews for Michael Facchiano Contracting have replaced bearings, anchor bolts, rail joints and portions of the concrete deck and slab and lifted the 600,000-pound bridge back into place at an estimated cost of $2 million. The 1,052-foot bridge, which crosses above Route 51, is used exclusively by Port Authority vehicles.
While the bridge has been closed, buses have been using local streets. Rail cars have been shifted from the Red Line to the Blue Line.
Riders can use a free rail shuttle between Overbrook Junction and Potomac Station. As operators are available, a free bus shuttle will take passengers from Potomac Station to Station Square.
Rail cars can’t resume using the bridge yet because Railworks Track Services LLC is replacing several feet of track, ties and ballast near the Fallowfield Station in Beechview. That $375,000 project has been delayed by rainy weather and should be finished by the end of the month.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.