Traffic on Interstate 79 north of the Neville Island Bridge will get more complicated beginning Friday evening when work starts to cross one northbound lane onto the south side of the highway to create an express lane to allow bridge and approach work.
The shift is part of the Pennsylvania Department of Transportation’s $26.5 million project to upgrade bridges and other structures in Glenfield, Sewickley Hills, Franklin Park, Kilbuck, Ohio Township and Aleppo.
Contractor Joseph B. Fay Co. is scheduled to start work at 7 p.m. Friday that will include traffic stops and single-lane restrictions. The crossover is expected to be finished by 11 a.m. Saturday.
Crews will create the crossover between the Neville Island Bridge and the Kilbuck Street on-ramp to shift the left, northbound lane of traffic to the southbound side of the highway beside the two southbound lanes. The north and south lanes will be separated by a barrier.
The crossover lane will be an express lane that continues without any exits until traffic is crossed back between the Red Mud Hollow Road overpass and Interstate 279.

That means motorists in the express lane won’t be able to exit at Mt. Nebo Road. Motorists in the right, local lane, which will not cross to the other side, will be able to use all exits, including Mt. Nebo.
Traffic also will be diverted slightly in the local lane at the Glenfield Road and Red Mud Hollow Road bridges to allow work on one side of the bridges.
Crews will create three emergency pull-off areas in the work zone along the southbound and express lanes and one along the northbound local lane.
The crossover, which is expected to last until late November, will allow workers to replace bridge decks, work on approaches, replace bearing pads and expansion dams, repair concrete substructure and upgrade downspouts. That work is expected to begin at 7 p.m. Monday evening.
A similar shift will occur next year to allow improvements on the southbound side of the highway before the work is finished in fall of 2023.
This won’t be the only traffic disruption in that area of I-79 this year. The Neville Island Bridge, which carries I-79 across the Ohio River between Glenfield on one side and Neville and Robinson on the other side, will be closed to southbound traffic for four weekends during the construction season, and ramps on the Glenfield side will be closed next fall as part of Trumbull Corp.’s $43 million project that also will finish next year.
Ed Blazina: eblazina@post-gazette.com, 412-s63-1470 or on Twitter @EdBlazina.