The city of McKeesport on Friday closed the Versailles Avenue Bridge after an emergency inspection revealed concerns about its deteriorating structure.
McKeesport Mayor Michael Cherepko said the immediate closure of the bridge over a portion of the city’s Sixth Ward was necessary after a structural engineering firm examined the bridge and suggested the stretch be shut down within 10 days.
“We received notification Thursday evening that we should be working to close this bridge within 10 days,” Mr. Cherepko said in a letter to the community posted on social media. “It is in the best interest of the safety of our residents that we are proactive in closing this bridge immediately rather than waiting for any time at all.”
The mayor said the city got in contact with structural engineering firm STV and the Pennsylvania Department of Transportation about the freeze-and-thaw the area has experienced this winter and the toll it has taken on local infrastructure.
STV inspected the Versailles Avenue Bridge in October and recommended McKeesport reduce traffic to one lane, advice the city followed. A follow-up inspection was scheduled for April because of the deteriorating conditions on one side of the bridge.
But the city moved the inspection to earlier this week because of the weather-related concerns, and STV advised that the bridge should be closed.
Read More
Concrete barriers were placed at both ends of the bridge Friday, and “bridge closed” and “detour” signs are expected to go up on Monday.
The detour will follow Coursin Street to Fifth Avenue to Evans Avenue to avoid residential areas, according to the city.
The McKeesport bridge closure comes just weeks after the Fern Hollow Bridge collapsed in Pittsburgh and at a time when a greater spotlight has been placed on the region’s dated infrastructure.
“With a recent collapse of a bridge in Pittsburgh, our concern was heightened on the issue of our local bridges,” Mr. Cherepko said. “We were in communication with STV and PennDOT regarding this year’s severe freeze-and-thaw cycle and the impact it can have on a damaged bridge. One day our temperatures are in the teens, and the next, they’re in the 50s. There’s a potential impact there that we aren’t willing to risk.”