Three projects worth $11.8 million — including a new transit center in Wilkinsburg, sidewalk improvements and temporary rubber extensions to increase the size of bus stops — will move forward using grants that Port Authority announced Thursday.

The authority received $8.2 million from the Southwestern Pennsylvania Commission for the work and will supplement it with additional money from the state and Allegheny County. The commission oversees transportation funding for a 10-county region.

The largest project is construction of a $7.8 million transit center in Wilkinsburg, a major stop along the Martin Luther King Jr. East Busway. The station has large parking areas and platform stops for passengers, but the transit center would have a building and include other amenities such as ticketing machines.

Authority spokesman Adam Brandolph said the agency hasn’t determined whether the new center will be at the same location or be moved closer to the Wilkinsburg business district. The agency will begin a study of the entire busway this spring to determine if it should improve stations, relocate them or create new ones.

Advertise with us

The new station will be built after the study is done using a $5.4 million federal Congestion Mitigation Air Quality Program grant, contributions of $2.1 million from the state and $260,000 from the county. The county said the Wilkinsburg station will be modeled after the one scheduled to open in a few weeks in McKeesport.

Another $2.5 million grant from the same program will help fund a $3.6 million program to fix sidewalks that provide access to bus stops. That issue was cited as a major concern last year as the agency developed its 25-year plan known as NEXTransit.

Mr. Brandolph said improvements could be done on property owned by Port Authority, municipalities or private owners with approval. Money for that work, including $981,000 from the state and $119,000 from the county, will be available for work in 2025.

The third grant will be used to buy eight extension pads that can be used to create a larger waiting area at busier bus stops. The rubber pads are similar to sidewalk bumpouts and are used to keep sidewalks open for pedestrians.

The authority is using a similar pad now on Liberty Avenue at Smithfield Street. Mr. Brandolph said the pads are designed to be used temporarily to determine if a more permanent solution like a sidewalk bumpout is needed in an area and could be used anywhere on the authority’s system.

Advertise with us

The authority received a $280,000 grant from the federal Transportation Alternatives Set-Aside Program, plus $120,000 from the county as a 50% match. The agency expects to begin the project in 2023.

Ed Blazina: eblazina@post-gazete.com, 412-263-1470 or on Twitter @EdBlazina.