Port Authority’s Saw Mill Run Boulevard Bridge will be closed for at least several more weeks after water infiltrated a concrete support, froze and expanded, causing the bridge to shift several inches last week, the authority announced Thursday.
Crews from GAI Consultants and Michael Facchiano Contracting have been examining the bridge since an employee discovered a gap in the surface Friday morning. The bridge, part of the South Busway used exclusively by Port Authority buses and light rail vehicles in Mount Washington, was closed immediately and vehicles have been rerouted.
Authority spokesman Adam Brandolph said experts haven’t determined how the water got into the support and are still deciding how extensive the work will be to fix the problem. The authority knows the bridge will be closed for several weeks, but it could be longer depending on what is required to fix it.
“We obviously will not be opening it until we can be sure it is safe for our buses and light rail trains,” he said.
Last week, crews removed a portion of the concrete bridge deck to get to the bridge's superstructure. They also had to remove overhead power lines, used to supply electricity to light rail vehicles, to create a safe work space.
The 1,052-foot bridge was built in 1977 and was rated in satisfactory condition at its last inspection in September 2020.
Read More
The closure has created separate detours for light rail vehicles and buses. Rail cars have been shifted from the Red Line to the Blue Line using a free rail shuttle between Overbrook Junction and Potomac Station, and a free bus shuttle is operating between Potomac Station and Station Square, each running every 20 to 30 minutes.
Buses are using local streets instead of the busway.
Regular traffic on Route 51/Saw Mill Run Boulevard under the bridge shouldn’t be effected.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.