Although his employees at Allison Park Contractors are going to have to learn new ways to work, Joe Zottola said he’s thrilled the Pennsylvania Department of Transportation will be starting or restarting $98.96 million of road construction work that’s been suspended since March 17 by the COVID-19 virus.

The agency announced Friday the 18 projects in Allegheny and Beaver counties that it considers “critical” to providing access to areas or important routes so that goods can move freely during the virus emergency. Half of the projects released for PennDOT’s District 11 will involve slide remediation work, some of it involving slides that occurred as much as two years ago as a result of record rainfall in the region.

The local projects are among 61 that will resume work across the state after Gov. Tom Wolf suspended all projects to help limit social contact to slow the spread of the deadly virus.

Cheryl Moon-Sirianni, District 11 executive, said the projects were chosen because not only are they important to the region, but also because slide remediation work often can be done with individual workers operating heavy equipment and having little interaction with other workers.

Advertise with us

Ms. Moon-Siriani said contractors will have to complete an extensive outline of their plans to keep employees safe from the virus and participate in a series of video conferences with PennDOT safety officials before work can begin.

“They have to send in a COVID-19 Safety Program to be approved before they can start,” she said. “I think the contractors are very aware of the need to keep their employees safe.”

Read More

Two projects, slide remediation work on Northern Pike in Monroeville and Lime Hollow Road in Penn Hills will resume April 13, and other projects will start “soon,” Ms. Moon-Sirianni said.

Mr. Zottola, who’s company has the Northern Pike project, said he’s going to spend the next week teaching workers the new protocols so they are ready when work resumes. In addition to being the company’s vice president, he’s the safety coordinator.

“Is it going to be difficult? Sure,” Mr. Zottola said. “ It’s pretty intense. There’s a lot of new stuff we have to do.

Advertise with us

“I’ll have a hazard checklist to go down when everybody arrives at the site so we can keep everybody safe every day.”

The new protocols include having employees take their temperature daily before they leave home and have it taken again when they arrive at work. The job site will have hand-washing stations and sanitary wipes, employees will eat lunch separately, and everyone will have masks available.

In addition, the contractor will post signs at each end of the project to notify the public that employees are using safe practices while they work.

Mr. Zottola said the Northern Pike project will put six people back to work: two operators, three laborers and a supervisor. In a normal year, the company has about 60 crew members at this time of year and as many as 110 in mid summer.

“It’s a lot of operator work, so we don’t have a lot of contact,” he said. “It’s easier [to maintain a safe distance] on this kind of job than when you have to build a bridge or build a sidewalk.”

Advertise with us

Brian Miller, president of Plum Contracting Inc., said his company has been authorized to resume four state projects, including a landslide on Hulton Road in Penn Hills and the second year of major renovations to the roads, bridge and bike trails at Ohiopyle State Park.

“We have about a week’s worth of prep work to do to get ready for this,” he said. “There’s a lot of thought going into how we’re going to do this even before we get to the site.”

Ms. Moon-Sirianni said it’s too soon to say whether additional work will be added because it’s not clear how long the health emergency will last.

This round of work also will include remediating landslides on Scenery Drive in Elizabeth Township, Larimer Avenue in Wilkins, Steubenville Pike in North Fayette, Lime Hollow Road in Penn Hills, Midland Road in Ohioville, and Frankfort Road in Hanover. The projects in North Fayette, Monroeville and Hulton Road in Penn Hills had been scheduled to start the day before PennDOT announced the suspension of work.

Other projects include resumption of the $31.3 million Elizabeth Bridge rehabilitation, the start of work on the $12.5 million replacement of the Kenmawr Bridge on South Braddock Avenue joining Rankin and Swissvale, and a $12 million project on Route 22 in Monroeville.

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.