The Elizabeth Bridge reopened Friday evening after crews were able to install supports to replace a temporary bracket that failed Thursday.
The Pennsylvania Department of Transportation had announced late Thursday that the bridge carrying Route 51 between Elizabeth and West Elizabeth borough would be closed indefinitely to its 25,000 daily users.
The bridge has been undergoing rehabilitation for the past two years, including the replacement of support cables that run from the arch to the bridge deck. To replace the cables, steel rods providing temporary support are attached to the arch and deck with brackets. One of those brackets failed, causing the concern and the bridge shutdown.
But PennDOT, the contractor, and consulting engineers worked around-the-clock to design and install a secondary system providing a redundant safety measure and that allowed the bridge to reopen, said Cheryl Moon-Sirianni, PennDOT’s executive for Engineering District 11.
“Multiple engineers have scrutinized the redesign, inspected the new redundant system, and conducted tests on the bridge,” PennDOT said in a news release Friday evening.
“I want to thank motorists for their patience during the bridge closure,” Ms. Moon-Sirianni said. “As the public’s well-being is our highest priority, the Department believed the best course of action was to close the bridge until we were completely confident that traffic could safely use the structure.”
Before cable replacement work can resume, modifications to the temporary support system will be analyzed and enhanced, PennDOT said.
On Thursday afternoon, as crews for Swank Construction shifted the weight of the bridge deck from the cables that regularly hold it in place to temporary metal brackets, a two-foot section of a bracket buckled, said Jason Zang, assistant executive for construction for PennDOT’s District 11. The deck weighs about 160,000 pounds, he said.
“A bracket failed. It bent, basically,” Mr. Zang said.
Crews shifted the weight back to the cables, which were scheduled to be replaced, and PennDOT conducted an emergency inspection Thursday evening that led to closing the bridge.
Mr. Zang said the failure occurred in a two-foot section of a 40-foot bracket. Instead of just replacing the bracket, PennDOT designed a new piece with “a second redundancy” to prevent the issue from occurring again.
Swank began work in October 2017 under a $31.3 million contract that has included concrete deck and barrier replacement, steel repairs, expansion dam replacement, bearing repairs, concrete substructure repairs and painting. Five other structures at the bridge also were rehabilitated.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 on on Twitter @EdBlazina.