An old adage often heard in Western Pennsylvania can be applied to an upcoming city project that will close Commercial Street: Temporary inconvenience, permanent solution.
Commercial Street, which serves as the main connection between Squirrel Hill and Swisshelm Park, had been the scene of incremental land movement for years. But large amounts of rainfall and landslide activity made the degree of deterioration worse.
“Part of the issue has been the land subsidence observed,” said Karina Ricks, director of the city's Department of Mobility and Infrastructure.
Ms. Ricks and City Councilman Corey O’Connor attended a meeting on Monday night to update residents about the project and its future plans at the Sarah Jackson Black Community Center in Swisshelm Park.
The infrastructure department has completed design plans to construct 80 feet of soldier pile wall and reconstruct the affected portion of Forward Avenue.
Ms. Ricks has said the area has had problems for more than 20 years. The city installed a support wall below the road surface and has extended it twice over the years.
Record rainfall in the early months of 2018 — as well as an intense freeze-thaw cycle — wreaked havoc along Commercial Street and elsewhere in the city. Commercial Street and Forward Avenue were shut down three times in the span of two months because of potential landslides. More than a dozen landslides were reported in the city during the period.
The project, which is estimated to cost $600,000, went out for bid on Sept. 18. Bids will be opened Oct. 9. The projected time frame for the road closure is November through February 2020. The project completion date is set for May 1. Project funding will come from the city’s capital budget. The road also may be closed for 10 days next spring for paving, something Mr. O’Connor has said is sorely needed.
Jersey barriers will be placed on the Parkway East to guard against more potential shifting of the hillside from above.
Mr. O’Connor, whose district includes Swisshelm Park, said it was originally hoped that the project would begin in August. However, the Pennsylvania Department of Transportation did not approve the highway occupancy permit until last month. PennDOT is a partner in the project.
Ms. Ricks said detours will be posted and will involve jurisdictions outside the city.