For the third time in a year, thousands of South Hills commuters will face significant delays in their bus and light rail trips beginning next Friday.
At least this time, there’s some warning and a fixed date for the hassles to end.
Port Authority will conduct a month-long, $1.8 million project to replace 480 feet of track and concrete between the Mount Washington Transit Tunnel and South Hills Junction. Michael Facchiano Contracting will work 24 hours a day to complete the project by Aug. 22.
The work will be done in two phases, one on each side of the track, from 7 p.m. July 26 through Aug. 11 and Aug. 12 through Aug. 22. It is expected to cause significant delays for about 10,000 light rail riders and 5,000 bus riders on weekdays and 5,000 light rail and 2,000 bus riders on weekends.
Last year, the authority’s Blue Line Library had service interrupted for three months between the Lytle and Library stations after heavy rains in June caused more than $5 million of damage to the track and a light rail car. In August, the full light rail system had to be detoured for 20 days when a Norfolk Southern train derailed, dropping material that damaged tracks and electrical wiring at Station Square.
For this project, inbound light rail service will be provided via the normally dormant Allentown line, but that won’t provide service to Station Square. To get there, riders will have to go to the First Avenue Station and get on an outbound light rail car to Station Square.
Read More
Inbound passengers at Station Square will board a rail shuttle on the inbound platform during Phase 1 and on the outbound platform during Phase 2.
On the outbound side, light rail cars will use the Mount Washington Transit Tunnel from the start of service until 11 p.m., when service will switch to the Allentown line. Because there will be no service to Station Square after 11 p.m., outbound customers will use a rail shuttle from Station Square to First Avenue, then board an outbound light rail car.
The work also will affect nine buses that regularly use the South Busway (Routes 39, 40, 41, 44, Y1, Y45, Y46, Y47 and Y49). The last inbound stop before buses are detoured will be the South Busway at Palm Garden.
That means inbound buses won’t serve these stops: South Busway at South Hills Junction; Station Square Station at South Busway Slip Ramp; East Carson at Smithfield. Additionally, Route 44 will be unable to serve the stop at the South Busway at Haberman Ramp (at South Hills Junction).
The authority will establish a temporary stop at the Wabash Tunnel Ramp at the Monongahela Incline on West Carson Street.
On outbound bus trips, the last stop before vehicles are detoured will be East Carson Street at Station Square. Buses will be unable to serve the stop at South Busway and South Hills Junction.
A temporary stop will be established at Warrington opposite Boggston (at the top of the sidewalk that comes up from South Hills Junction).
To help commuters, the authority has established a special, dedicated Customer Service Construction Information Line that can be reached at 412-566-5544. A customer service representative will staff this line from 6 a.m. to 7 p.m. on weekdays and from 8 a.m. to 4:30 p.m. on weekends.
For help with trip planning or general questions, customers are encouraged to call Customer Service directly at 412-442-2000.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.