The HOV lanes on the Parkway North/Interstate 279 are closed through mid-June as part of the reconstruction of the highway.
The Pennsylvania Department of Transportation closed the lanes around 3 a.m. Tuesday.
The HOV lanes have been used for mainline traffic the past two years so crews from Trumbull Corp. and Lindy Paving could work on the northbound and southbound lanes.
The work on the lanes will involve paving, concrete patching, installing an anti-icing system, strip sealing expansion dams and putting in a new lane control system.
The lanes run from Pittsburgh’s North Side to McKnight Road in Ross.
The $87.9 million Parkway North project should be finished by the end of June.