The HOV lanes on the Parkway North/Interstate 279 will close for about 10 weeks beginning Tuesday.

The Pennsylvania Department of Transportation said the lanes will close at 3 a.m. Tuesday until mid June as part of the three-year reconstruction of the highway. The HOV lanes were used for mainline traffic the past two years so crews from Trumbull Corp. and Lindy Paving could work on the northbound and southbound lanes.

The work will involve paving, concrete patching, installing an anti-icing system, strip sealing expansion dams and putting in a new lane control system. The lanes run from Pittsburgh’s North Side to McKnight Road in Ross.

The $87.9 million project should be finished by the end of June.