The Rachel Carson Bridge, the second of the Three Sister spans between Downtown Pittsburgh and the North Side, was closed Monday as it undergoes a major overhaul.
The span was closed to vehicular and pedestrian traffic at 6 a.m. Monday as contractors Brayman Construction and Advantage Steel and Construction begin about 19 months of work. The $23.3 million project includes a new concrete deck, structural steel repairs, painting, new bridge and architectural lighting, replacement of expansion dams and drainage systems and new sidewalks.
One major difference from the previous project involving the Andy Warhol Bridge, completed in November 2017, is replacing the sidewalks, said Michael Dillon, the county’s assistant director of public works. As a result, pedestrians can’t use the bridge during construction.
When the Carson project is finished in September 2020, the bridge will have a new lane configuration. Rather than two lanes in each direction, there will be one lane each way with wider shoulders in the middle of the bridge and two exit lanes at each end so that drivers have a turning lane.
In late 2021, the county expects the same kind of rehabilitation for the Roberto Clemente Bridge. That project will have its own set of challenges because the bridge provides the primary pedestrian access to PNC Park from Downtown.
The Warhol, Carson and Clemente bridges are two blocks apart and the only trio of identical bridges in the world. They also were the first self-anchored suspension bridges in the U.S/