Building the next section of the Southern Beltway will involve a challenge the Pennsylvania Turnpike doesn’t often deal with: acid mine drainage.

Officials told residents that acid mine drainage near the construction of two curved bridges over Noblestown Road in Robinson Township, Washington County, will be one of the first things to be dealt with after work begins on the next section of the toll road early next year. Residents reviewed plans for the project during an open house Wednesday at the Fort Cherry Golf Club near McDonald.

Trumbull Corp. received a $116.2 million contract to build 2.75 miles of the highway from Quicksilver Road to the Panhandle Trail.

Steve Hrvoich, the turnpike’s construction engineering manager, said it’s rare for the agency to deal with acid mine drainage. But engineers have been studying the area for several years in anticipation of the project to develop a plan to deal with it.

Advertise with us

That plan calls for installing a passive limestone treatment system, Mr. Hrvoich said. Crews will build a collection basin 10 to 12 feet deep filled will limestone, which the contaminated water will pass through for mitigation.

John Nemmer, Trumbull’s project manager, said crews will complete the drainage system and let it sit for six months so it can settle before bridge construction begins.

“Those two bridges we will be working on for two years,” Mr. Nemmer said.

Another early part of the project will be installing an access road off of Cooks Road for the McDonald Sportmen’s Association.

This project is a middle section of the 13-mile, $800 million toll road that will run from Route 22 to Interstate 79 and provide an alternate route to Pittsburgh International Airport. The section will be done in early 2021 but it won't open until most of the highway is finished in early 2022.

Advertise with us

Work on this section will feature an interchange on former sportsmen’s club land that will link by connector roads to Route 980 to the north and Noblestown Road to the south. The turnpike paid $5 million to buy 70.9 acres from the club for the interchange.

In addition, twin steel curved girder bridges at the eastern end of the site will cross over Noblestown Road and the Panhandle and Montour trails. The structures will have seven piers, some more than 100 feet high, and the westbound side will be 1,524 feet long, the eastbound side 1,448 feet.

Crews will have to move about 3.3 million cubic yards of earth to flatten hills and fill in valleys to create a smooth road surface.

Only one more contract remains to be awarded for the beltway project: construction of a complicated interchange with I-79. The turnpike will open bids Dec.19 for work that will include digging a new valley beneath the existing interstate, installing bridges across that valley and building the interchange with the beltway under the bridges at a cost of $150 million to $200 million.