The Pennsylvania Department of Transportation will close the inbound ramps from Squirrel Hill and Greenfield to the Parkway East/Interstate 376 for a week beginning Friday evening, inconveniencing 20,000 motorists who use the ramps every day.
The belief is that the week-long ramp closures will reduce the number of times crews will have to close the full inbound parkway for an entire weekend, inconveniencing 100,000 a day, said Steve Cowan, PennDOT’s spokesman for District 11. If that’s successful, the agency will do the same thing again for a week in November, Mr. Cowan said.
Swank Construction Co. has a $26.4 million contract to repave the highway and ramps between the Fort Pitt Bridge and the Edgewood-Swissvale exit, along with replacing bridge dams. As part of that contract, crews would be allowed to close the highway for up to 12 weekends over the next two years, six in each direction, a situation that historically has caused massive traffic jams.
As an alternative, beginning at 9 p.m. Friday, Swank will close the inbound Beechwood Boulevard and Forward Avenue ramps that provide access from Squirrel Hill and Greenfield through 5 a.m. Oct. 26. The closure will allow crews to work in the closed third lane of traffic created from the ramp to replace dams on bridges over Saline and Frazier streets.
“For six days, this is going to be impactful,” Mr. Cowan said. “For those six days, folks from Squirrel Hill and Greenfield are going to have to find a different route. They are going to have to allow extra time because it’s going to be slow-going.”
Police officers will be stationed at intersections to help move traffic through the neighborhood streets that ordinarily would get on the highway at Squirrel Hill.
Mr. Cowan said it remains to be seen whether the closure causes even more rush-hour backups on the main lane of the highway before the Squirrel Hill Tunnel or at the Oakland exit. Two lanes of traffic that exist before the tunnel will continue after the tunnel and the far right lane closure will end at least one-quarter mile before the Oakland exit.
“We’re not limiting any lanes on the main line, so we just don’t know” whether the work will cause additional traffic jams," Mr. Cowan said..
If this process works, Mr. Cowan said, the contractor will take similar steps to close the same ramp to do work on another lane in the same area. Replacing the bridge dams is crucial, Mr. Cowan said, because the bridges could be facing weight restrictions within six months due to deterioration.
Mr. Cowan said the department won’t know how many less weekend closures will result from the week-long closures until the contractor is able to do a full week of work.
The contractor also is expected to do additional inbound work this weekend, but the details won’t be announced until Thursday.
Ramp detour:
Beechwood Boulevard/Forward Avenue on-ramp to westbound (inbound) Parkway East (Ramps A and C)
▪ Follow Beechwood Boulevard past the closed ramp
▪ Take the ramp to eastbound I-376 toward Monroeville
▪ Take the Edgewood/Swissvale off-ramp (Exit 77)
▪ Bear right toward Swissvale
▪ Turn left onto Monongahela Avenue
▪ Turn left onto South Braddock Avenue
▪ Take the ramp to westbound I-376 toward Pittsburgh

Alternate routes:
Beechwood Boulevard/Forward Avenue (Ramp A) alternate route:
▪ Continue on Beechwood Boulevard past the closed ramp
▪ Turn left onto Ronald Street
▪ Turn right onto Greenfield Avenue
▪ Continue straight onto Second Avenue
▪ Turn right onto Bates Street
▪ Turn left onto the Boulevard of the Allies
▪ Take the ramp to westbound 376 toward Downtown/Fort Pitt Bridge
Forward Avenue (Ramp C) alternate route
▪ From Forward Avenue, take Murray Avenue northbound to Forbes Avenue
▪ Turn left onto Forbes Avenue
▪ Turn right onto South Bellefield Avenue
▪ Turn left onto Fifth Avenue
▪ After the Fifth Avenue intersection with Craft Avenue, motorists should stay in the left-hand travel lane (not the bus lane) and turn left onto the ramp toward westbound 376
▪ Merge onto the Boulevard of the Allies
▪ Take the ramp to westbound 376 toward Downtown/Fort Pitt Bridge