Tuesday is the re-scheduled end date for the 2½-year-long Liberty Bridge reconstruction project, but motorists may encounter “as needed” lane restrictions for one more week.

Two items remain on the list for the bridge project — sidewalk sealing and repairing a pedestrian railing struck by a car, said Steve Cowan, spokesman for PennDOT’s District 11 office.

“These are extremely minor items and should have little impact to motorists,” Mr. Cowan said.

The Liberty Bridge has been under construction since April 2016. The roughly $80 million project involved replacing the bridge deck, repairing structural concrete and steel, installing a new overhead alternating lane control system, and adding a new coat of paint and signs.

Advertise with us

A September 2016 fire — that buckled a support chord — closed the bridge, snarling traffic throughout the city for 24 days as the bridge’s 55,000 daily users had to detour. The fire began when hot slag from a steel-cutting operation fell onto plastic piping stored on site.

Joseph B. Fay Co., which oversaw the project, paid $5.8 million for emergency bridge repairs following the fire.