Elliott Group’s steam turbine only traveled 1.8 miles through the streets of Donora Friday, but moving the 171-ton machine even a short distance required a sophisticated operation.

A 62-foot trailer with 80 tires transported the steam turbine — Elliott Group’s largest ever — from the company’s Donora service center, through the town, to the Monongahela River. Crews had to move power lines and utilities as they squeezed the 24-foot tall turbine through the town. J. Supor & Son Trucking & Rigging Co., based in New Jersey, headed the operation.

Crews on Saturday will load the turbine onto a barge that will transport it to its final destination, a petrochemical complex in Monaca currently under construction, according to a press release from Elliott.