Flood damage from the torrential rains that swept through the region Wednesday night has shut down light-rail service in the South Hills Thursday.

Service along the T’s Blue Line from Washington Junction to the Library station has been suspended in both directions, according to the Port Authority of Allegheny County.

Rail service will only operate from South Hills Village on the Red Line in both directions and through Allentown to Downtown and North Shore, the Port Authority said early Thursday. Service from Washington Junction will also use the Red Line track in both directions.

Shuttle buses have been running between Library and Washington Junction and along Route 88, although the Port Authority was advising commuters to consider using nearby bus routes.

Advertise with us

“Please allow for extra travel time due to these issues,” the transit agency noted.

By 6:30 a.m. Thursday, crews reopened the Mount Washington Transit Tunnel so buses, and the Red Line was no longer detouring via Allentown.

“The flooding has caused significant damage to the rail system.”

The Port Authority shut down all rail service Wednesday night as.torrential downpours caused flooding throughout the Pittsburgh region.

Authority spokesman Adam Brandolph said damage to the rail service included a mudslide at the south end of the Mount Washington transit tunnel and an energy tower problem that caused crews to de-energize the entire rail system in the city.

Advertise with us

Those needing help planning their commutes can contact the authority’s customer service at 412-442-2000 or 412-231-7007 for TTY.

Other travel routes impacted due to flooding and debris left behind:

▪ Flood damage has closed Morrow Road Bridge in Upper St. Clair. Detour signs are posted.

▪ Becks Run Road Is closed between Brownsville Road and Hopeland Street due to flooding

▪ Brownsville Road bridge is down to one lane between McCorkle Road and Greenbriar Drive