Contractors are making good progress on installing a retaining wall along a section of Route 30 in East Pittsburgh that collapsed in early April and may meet the goal of having the highway reopened by the end of June.

Crews Friday were performing tension tests on steel anchor rods that have been installed to hold precast concrete panels. That testing could take a few days, but if the rods are properly anchored in, bedrock crews can begin placing the panels, dumping 40,000 cubic yards of fill and rebuilding more than 500 feet of the highway, Cheryl Moon-Sirianni, PennDOT’s district executive for Allegheny, Beaver and Lawrence counties, said Friday.

Speaking after another event with Gov. Tom Wolf to highlight an expanded pothole patching and road paving program this year, Ms. Moon-Sirianni and Allegheny County Executive Rich Fitzgerald praised consultant Gannett Fleming Inc. and contractor Golden Triangle Construction for working as much as seven days a week to fix the highway. Golden Triangle has a $6.54 million emergency contract for the work.

“They have moved heaven and earth to get that project done,” said Mr. Fitzgerald, who said such a project could take as long as two years to complete. “It’s nothing short of spectacular what they are doing.”

Advertise with us

Ms. Moon-Sirianni called the project “a testament to teamwork” among her department, the consultant and the contractor, as well as suppliers who have have met an expedited schedule for material. Mr. Wolf said the state plans to submit the Route 30 incident — which includes several million dollars more for emergency housing for residents displaced by the highway collapse — along with other landslides across the state to federal officials for emergency funding since officials believe all of them are tied to record rainfall in March and April.

The highway carries 25,000 to 30,000 vehicles a day and is a major artery to the Parkway East from North Versailles, East McKeesport and North Huntingdon. It has been closed between the outbound exit at East Pittsburgh and the Westinghouse Bridge since April 7, when three lanes of the highway fell when the hillside under it collapsed.

The debris destroyed two of five apartment buildings in the Electric Avenue Apartments and a hillside house on Beech Street Extension was so badly damaged it had to be razed. Ten residents will need permanent replacement housing but 21 others should be able to return to the remaining apartment buildings when the work is done.

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.