Here’s a list of projects PennDOT expects to be working on in 2018 in Beaver County:

Projects continuing from 2017 with minor work remaining

Vanport Bridge Rehabilitation

Minor work, including an epoxy overlay on the bridge deck and lighting improvements, requiring single-lane restrictions, will occur this spring on the $15.87 million Vanport Bridge Rehabilitation project. The project includes the painting of the structure, a deck overlay, new bearings, dam replacements, lighting improvements and electrical upgrades on the bridge that carries I-376 over the Ohio River in Vanport and Potter townships.

Advertise with us

Projects continuing from 2017 with major work remaining

Route 65 – Allegheny County to Crows Run Road

The $8.25 million Route 65 roadway resurfacing project will resume in March and continue through May 2018. This year’s work includes curb repairs, driveway adjustments, ADA curb cut ramp installation, inlet work and final paving. Long-term lane restrictions will occur between Baden and Crows Run Road in Conway from March through April. Completed work includes milling, guiderail updates, bridge and retaining wall preservation, sign structure maintenance and signal improvements. The overall project is expected to be completed in late spring 2018.

I-376 Beaver Valley Expressway – Chippewa to Allegheny County

Highway lighting at the Center interchange, fiber optic cable installation, guiderail improvements and sign installation work remain on this $18.34 million improvement project on I-376 between Allegheny County and the Chippewa interchanges. Off-peak daylight single-lane restrictions will occur in various locations throughout the corridor beginning in March. The overall project is expected to end in the early summer of 2018. Concrete pavement restoration and milling and resurfacing have been completed.

Advertise with us

Freedom Road Upgrade

The next phase of the $19.43 million Freedom Road upgrade began in mid-February with the closure of Freedom Crider Road in New Sewickley. The closure will allow crews to conduct utility relocation, the completion of the Snake Run and Park Quarry bridges, asphalt paving, excavation work, guiderail and sign updates, and drainage improvements. Work began in 2016 on this project, which includes realignment and roadway reconstruction on Freedom Road in addition to the reconstructing of Crows Run Road (T-575) and relocation of Freedom Road to follow the T-575 corridor. The project will enhance safety and address substandard roadway features. Additionally, this multi-year project includes bridge and structure replacement, utility and stream relocation, wetland mitigation and other various construction activities. The overall project will continue into 2019.

Route 351 Koppel Bridge Replacement

The $27.58 million Route 351 Koppel Bridge replacement project continues in 2018 with steel erection, and pier and retaining wall construction to the bridge connecting Koppel to North Sewickley over Beaver River. Traffic will be maintained on the existing bridge during the construction of the new bridge. An approximate three-month closure with detour will occur in the summer of 2019. Additional work includes signage, pavement markings, drainage and guiderail installation.

Projects starting construction in 2018

Advertise with us

Route 18 – Frankfort Road to Rochester-Monaca Bridge and Route 3002 Old Brodhead Road – Frankfort Road to Broadhead Road

Milling and resurfacing work is expected to begin in June on the estimated $10-12 million project to improve Route 18 and Old Brodhead Road in Monaca and Center. Work on Route 18 will occur between the Rochester-Monaca Bridge and the new I-376 Monaca/Shippingport interchange. Additional improvements include guiderail upgrades, signal improvements, drainage work, shoulder repairs, signal updates and slide remediation work on Old Broadhead Road. Additionally, milling and paving will occur on a section of Pennsylvania Avenue in Monaca. Restrictions include off-peak single-lane restrictions in the four-lane section of Route 18 and single-lane alternating traffic in two-lane areas. The project will continue through late 2019.

Route 18 – Fifth Avenue to YMCA Drive and Route 6018

The estimated $11-12 million Route 18 (Third Avenue) roadway resurfacing project will begin in June in Beaver County. Work will occur between 5th Avenue in New Brighton and the Veterans Memorial Bridge/YMCA Drive in Rochester. Work includes milling and resurfacing, full-depth reconstruction, drainage, ADA curb ramp installation and signal improvements. Short-term and long-term restrictions will occur with at least one lane of traffic maintained in each direction. Additionally, work will occur on Route 6018 that includes portions of Rhode Island Avenue, the Rochester roundabout, Brighton Avenue and Delaware Avenue. Improvements on this section include milling and resurfacing, ADA curb cut ramp installation, signal upgrades, concrete patching and overlay, and ramp work requiring closures and detours. The overall project will be completed in fall 2019.

Route 1022 Sunflower Road Slide Remediation

Advertise with us

Sunflower Road slide remediation work between 11th Avenue and 44th Street in Pulaski Township will begin in mid-March. The estimated $500,000 project will include work to repair a landslide with Geosynthenic Reinforced Soil and pavement reconstruction in the area of the slide. A 90-day full closure and detour of the road is anticipated to begin in late March.

Route 1026 Reno Street Slide Remediation

Work on the Reno Street slide remediation project between Porter Lane and Highland Road in Rochester Township is included in a group project beginning in November 2018 until May 2019. The estimated $300,000 to $605,000 project will include the installation of a rock slope to repair a landslide, reconstruction of the existing pavement and drainage improvements. Traffic will be detoured during construction.

Route 4012 Bradys Run Road Slide Remediation

Work on the Route 4012 Bradys Run Road slide remediation project between May Road and Grange Road in Brighton Township is included in a group project beginning in November 2018 until May 2019. The approximate $425,000 project will include the installation of a rock slope to repair two landslides and pavement reconstruction. During construction, traffic will be detoured.

Advertise with us

Route 1005 Chapel Drive Bridge Rehabilitation

Work on the Chapel Drive Bridge over a branch of Connoquenessing Creek in North Sewickley is anticipated to begin in the summer 2018 and last approximately six weeks. The estimated $100,000 to $200,000 project will replace the existing corrugated metal pipe culvert with a new precast reinforced concrete box culvert. To allow crews to place the new culvert and tie into the existing roadway, a full closure and detour in the bridge area will occur.

Route 1009 Fombell Road Bridge Replacement

Minor work is expected to begin in 2018 on the estimated $1-2 million bridge replacement project on Fombell Road over Camp Run in Franklin Township. In addition to the superstructure replacement, which will require a detour, substructure repairs and approach roadway work will occur. The project is expected to be finished by September 2019.

Route 4005 New Galilee Road Bridge Rehabilitation

Advertise with us

Work on this estimated $1-2 million bridge project on New Galilee Road over the north fork of Little Beaver Creek in Darlington is expected to begin in August. Bridge rehabilitation work including concrete repair, scour protection, superstructure replacement, and approach roadway work will occur. Traffic will be detoured during construction. The overall project will continue through mid-November 2019.

Route 4012 Bradys Run Road Bridge Replacement

The Bradys Run Road bridge project will replace two structurally deficient bridges in Chippewa between May Road and Darlington Road. Work will begin with the bridge closest to May Road, with a full closure and detour from late August through mid-November 2018. Following a winter hiatus, work will continue with the replacement of the bridge closest to Darlington Road with a full closure and detour from mid-March through July 2019. The $2-3 million project is anticipated to be completed in late September 2019.

Route 4020 Dutch Ridge Road Bridge Replacement

This estimated $4-5 million bridge replacement project over I-376 (Beaver Valley Expressway) in Brighton Township will have minor work begin this year with the majority of construction occurring in 2019. Work will include a bridge replacement and minor approach roadway work. Traffic will be detoured on the bridge and traffic stoppages will occur on I-376 for beam removal and erection. The overall project is expected to conclude in mid-November 2019.

Advertise with us

Group Resurfacing Contracts

The routes listed below will be milled and resurfaced with drainage improvements and minor rehabilitation in 2018 under contract group projects (work areas may be subject to change):

• Sunflower Road (Route 68) from Virginia Avenue (Route 1039) in Rochester Township to Glen Eden Road (Route 989) in New Sewickley.

• Old Darlington Road (Route 4013) from approximately 1/3 mile north of Marlene Road to Wallace Run Road (Route 551) in South Beaver.