Beginning Monday, motorists who use Interstate 279/Parkway North to get out of Downtown Pittsburgh will face a series of traffic headaches through August with the second year of the $87.9 million project to rehabilitate the 30-year-old highway.

After a season of work on the southbound lanes last year, work switches to the north lanes between the North Side and Camp Horne Road, starting with the closure Monday of the HOV lanes. The lanes will remain closed until March 11 while crews prepare a crossover near the McKnight Road exit so northbound traffic can use the HOV lanes there.

Also on March 11, barriers will be installed at the Perrysville Avenue interchange to allow one lane of northbound traffic to use the southbound lanes as an express route with no exits until just past Camp Horne Road. Motorists who want to exit at Perrysville, Bellevue/West View and Camp Horne will have to stay in the right, local lane.

Those are the first of a series of changes outlined Tuesday by Cheryl Moon-Sirianni, PennDOT’s executive for District 11, that will challenge motorists trying to head north from the Downtown area during the construction season. Trumbull Corp. and Lindy Paving are the general contractors for the complicated project, which includes resurfacing the highway, upgrading 30 bridges and extending two entrance ramps to improve traffic flow.

Advertise with us

Crews did similar work with similar changes in the traffic pattern on the southbound lanes last year.

“There’s more work being done this year, “ Ms. Moon/Sirianni said. “We will probably have more impacts than last year.

“It’s very difficult to conduct this project and maintain traffic. We’re trying to minimize the effect our work is going to have.”

One particular problem will be the closure of the southbound ramp from Route 65 onto I-279 from mid April until mid June for deck rehabilitation. Traffic probably will be detoured across the Fort Duquesne Bridge to Fort Duquesne Boulevard to the Rachel Carson Bridge, but that hasn’t been finalized.

“This is a very difficult movement and we’re looking at what the best detour would be,” Ms. Moon-Sirianni said. “That is a very complicated detour.”

Advertise with us

Once that work is done, traffic will be reduced to one lane for 60 days on the North Shore viaduct between the Route 28/Chestnut Street off ramp and the point where northbound Interstate 579 merges onto I-279 so crews can replace expansion dams and repair the bridge deck. That work should be done by August.

At Perrysville, the northbound exit ramp will be closed March 11 and traffic heading to that area will exit from the HOV lanes through the Perrysville park-and-ride lot through mid July.

The project also will extend the Interstate 579 entrance ramp by about 1,000 feet and the Madison Avenue ramp by 2,000 feet, although the work on Madison could be postponed until 2019. The ramp work is designed to create more distance between the entry points and improve traffic flow.

Ms. Moon-Sirianni said PennDOT will work closely with the city, the Pittsburgh Pirates and the Pittsburgh Penguins to provide as much access as possible to major events over the summer. After major evening events at PPG Paints Arena, the Bedford Avenue entrance to the HOV lanes will be open for two hours and traffic on the main line will be reduced to one lane for an easier merge.

One unique aspect of the work will be the experimental use of a traffic light on the northbound I-279 entrance ramp at Bellevue/West View. Under a project funded by the Federal Highway Administration, a traffic signal will change from red to green to allow one car at a time to merge onto the highway between 6 and 9 a.m. and 4 and 7 p.m.

Advertise with us

Motorists who use that area can sign up for an email newsletter about the project by emailing stcowan@pa.gov and writing “Subscribe — Parkway North” in the subject line.

Ed Blazina: eblazins@post-gazette.com, 412-264-2470 or on Twitter @EdBlazina.