The Pennsylvania Department of Transportation may break down its $200 million proposal to revamp the Parkway West near the Fort Pitt Tunnel into smaller projects because of the way funding is coming in.

For the past few years, the department has been doing early design work on a number of steps to reduce traffic on Green Tree Hill near the tunnel with a goal of doing the work as one project. That work would include major changes to the interchanges at  Banksville/Route 51, Green Tree and Carnegie.

But a $9.54 million grant for the Banksville portion of that project announced Wednesday by the Southwestern Pennsylvania Commission may change those plans, district Executive Cheryl Moon-Sirianni said Thursday. That grant will allow engineers to begin refining the design for that portion of the project ahead of the others, she said.

The department had hoped to move the projects along at the same time through funding from the federal FASTLANE program, but it was not funded in the latest round of grants. The department now will try to get funding through the regional or statewide Transportation Improvement Program, Ms. Moon-Sirianni said, but that won’t hold back the Banksville/51 section of work.

Advertise with us

“The Banksville part may be able to move head on its own,” Ms. Moon-Sirianni said.

The Banksville portion of the project involves adding a lane of traffic from the West End so traffic headed to the Parkway and to Banksville Road would have separate lanes and would move the Route 51 interchange farther up Green Tree Hill so exiting traffic wouldn’t get so close to the tunnel. It also would extend the outbound on-ramp from the new interchange as a right climbing lane for trucks interchange to the Parkway Center exit.

Construction is expected to cost about $35 million but there’s still no timetable when it will begin.

Ms. Moon-Sirianni said there are no plans to close off Banksville to traffic exiting the tunnel from Downtown.

“I know a lot of people feared they wouldn’t be able to use Banksville, but I can assure you that’s not going to happen,” she said.

Advertise with us

Remaking the Green Tree and Carnegie exits will have to proceed at the same time, Ms. Moon-Sirianni said. Right now, the entrance and exit lanes are too close in both directions and work to separate them must be done at the same time.