Problems with late delivery of equipment and existing equipment not functioning properly will delay implementation of the Port Authority’s cashless fare policy on the light rail system at least until December.

In a news release Wednesday, the authority said it doesn’t expect to receive 10 of the 20 new machines it needs to dispense prepaid ConnectCards until at least October. Once it receives the machines, the agency will test them to make sure they work before beginning a two-month educational campaign to prepare riders for the new system.

The machines, a key to moving ahead with the cashless fare system on the light rail trains that run between the South Hills and Downtown Pittsburgh, were expected to be delivered and installed in June. The authority initially projected a July start for the cashless system but more recently hadn’t settled on a beginning date.

“We thought we could start the system with 10 machines in place, but we don’t have them yet,” said authority spokesman Adam Brandolph.

Advertise with us

In addition to the late delivery, the authority also is having difficulties with the existing ConnectCard machines, new validation stations where riders will swipe their card before getting on the light-rail system and handheld machines enforcement officers will use to check whether riders have paid. Validation machines have been installed in some light-rail stations, but they aren’t being used yet.

The manufacturer has experts in Pittsburgh working to correct those problems, Mr. Brandolph said.

The authority’s entire fare collection system was designed in 2009 under a $32 million contract with Scheidt & Bachmann, a German company with U.S. offices in Lowell, Mass. It has an additional $1.2 million contract to provide the new ConnectCard machines.

In a news release, interim Port Authority CEO David Donahoe said it is important for all aspects of the system to be working properly before the cashless system begins.

“The goal of the policy is to make the customer experience better, but in order to make that happen, all of the equipment must be available, functional and reliable,” he said. “Because these items will take time to resolve, I’m not prepared to announce a new start date until I see the results of the work now underway, including field testing.”

Advertise with us

This isn’t the first time the authority has had problems with the Scheidt & Bachmann system. When it started using new fare boxes in 2010, the machines jammed taking cash and thousands of passengers received free rides until the authority temporarily returned metal boxes to collect fares.

Those problems eventually were corrected and the authority uses the system on all of its vehicles. As a result, it has to use Scheidt equipment for any changes or it wouldn’t be compatible, Mr. Brandolph said.

“It’s an entire system,” Mr. Brandolph said. “You just can’t buy things a la carte.”

Mr. Brandolph said Scheidt’s contract for the machines doesn’t have penalties for missing delivery dates, but it allows the agency to stop paying when certain deadlines aren’t met. The authority has paid about $425,000 so far, but it has stopped making payments until the equipment is delivered.

The validation machines and handheld tools enforcement officers will use were purchased under the initial contract but haven’t been used yet. Scheidt representatives are working on that system under the 2009 contract.

Advertise with us

Scheidt could not be reached for comment.

The authority announced the change to a cashless fare on the light-rail system about 18 months ago when it revamped its fare policy. In January, it switched to a flat fare of $2.50 for ConnectCard users, $2.75 for cash, and expected to go cashless on the light-rail system in July.

A coalition, which has challenged the enforcement of the fare policy by armed officers who will run criminal warrant checks, on riders who haven’t paid said the delay is a good idea. They met with the agency two weeks ago to ask for civil enforcement procedures by unarmed fare checkers rather than a criminal process, but they said they haven’t received a written response yet.

“Obviously, we think delaying is the right thing to do if the equipment isn’t available yet,” said Laura Wiens of Pittsburghers for Public Transit, one of four groups in the coalition.

“We hope they use this time to rethink the enforcement policy.”

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.