The Parkway East will close this weekend in both directions for construction of the new Greenfield Bridge above the highway.

The highway will close from 3 a.m. Saturday through 6 a.m. Monday between the Oakland and Wilkinsburg exits. Mosites Heavy Construction will use the closure to tighten connections on arches placed during last month’s closure and install metal decking to prepare the structure for paving in the spring.

The detours will be the same as closures last month, when crews placed new arches, and last December, when the old bridge was demolished. Outbound traffic will exit at Oakland and follow Forbes and Fifth avenues to Penn Avenue through Wilkinsburg to the parkway; inbound traffic should exit at Wilkinsburg to Penn Avenue to Fifth and back on the parkway in Oakland.

The inbound highway will be open to the Edgewood/​Swissvale exit for local traffic only.

Advertise with us

Police officers will be on duty to help keep traffic moving at key intersections.

Mosites has a $17.5 million contract with Pittsburgh to build the new bridge between Greenfield and Schenley Park.

This is the fifth and last Parkway East closure in connection with the bridge.

Traffic is expected to begin using the bridge again in June but construction on the underside of the bridge and the outbound side of the highway will continue through summer.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.