The Pennsylvania Turnpike will hold an open house Wednesday to discuss plans for the $76 million reconstruction of the toll road between the Cranberry and Warrendale interchanges.
The three-mile project in Cranberry and Marshall, scheduled for construction beginning in 2019, will involve widening the turnpike from two lanes in each direction to three lanes as part of the system’s overall $2.5 billion reconstruction program. The project will include expanding the median from 10 feet to 26 feet, which is the standard median size, from milepost 28 to milepost 31.
In addition, the project will replace bridges over Route 19, Mount Pleasant Road and an unnamed tributary of Brush Creek. Another bridge on that section of the turnpike, over Thorn Hill Road, was replaced last year.
Another aspect of the project will involve lowering about 525 feet of Mount Pleasant Road to provide the appropriate level of clearance under the turnpike bridge there.
New storm water facilities will be constructed, including two retention ponds, and a sound wall near the Warrendale interchange will be extended about 1,000 feet.
Turnpike spokeswoman Renee Vid Colburn said the project will require the turnpike to acquire about 15 properties. The owners have been notified and discussions are underway to determine how much property will be needed and how much they will be paid.
Construction is expected to begin in 2019 and take three construction seasons to complete. Traffic will be maintained during the project.
Construction on a similar widening project from milepost 44 to milepost 48 should be finished next year. The turnpike will seek bids next year for the same kind of work between milepost 40 and 44, which would involve two years of construction.
Plans will be on display from 6 to 8 p.m. in the cafeteria of Marshall Middle School, 5145 Wexford Run Road, Marshall. Officials recommend parking in the rear lot across from Marshall Elementary School and entering through doors by the gymnasium.
Turnpike officials and design consultants will be available to answer questions about the project on an individual basis.