If all goes well this weekend, the two large, curved pieces of green steel sitting along the outbound Parkway East near the Squirrel Hill Tunnel will look like a bridge by Monday morning.

The Parkway East will be closed in both directions from Friday night until 6 a.m. Monday so crews from Mosites Heavy Construction can set the arches for the new bridge above the road. An operator using a 370-ton crane will lift pieces of the arches and deck frame into place so a crew of 12 to 15 ironworkers can assemble them and place them on concrete abutments that have been under construction for several months.

“That’s what we’ve been doing all this week is prep work so the arches are ready to be put in place this weekend,” said Derrick Jeannerette, project manager for Mosites. “It’s going to be lifting all of these pieces and securing them.”

Because the work is being done above the highway, the Parkway East will be closed to through traffic in both directions from Oakland to Wilkinsburg. The detours will be the same as when the highway was closed between Christmas and New Year’s Day last year to demolish the old concrete bridge.

Advertise with us

“We know it’s an inconvenience to motorists [to close the highway], but this is the only way we can get this done,” said Guy Costa, Pittsburgh’s director of operations. The city owns the bridge and has a $17.5 million contract with Mosites to replace it.

For inbound traffic, the official detour begins at Wilkinsburg, where motorists will exit onto Penn Avenue and follow that to Fifth Avenue through Oakland and back onto the Parkway East. The highway will be open to the Edgewood-Swissvale exit at South Braddock Avenue for local traffic.

Outbound traffic will exit at Oakland onto Forbes Avenue, turn left on Bellefield, right on Fifth and right on Penn Avenue through Wilkinsburg to get back on the parkway.

Police officers will be on duty to help move traffic along the detour routes.

“We found from the previous closure, people who live around here will find their own alternate routes,” Mr. Costa said. “People who aren’t familiar with the area will follow the detours.”

Advertise with us

This weekend is the first of two closures for assembling the arches and decking frame. The second is scheduled for just after midnight Nov. 19 following Light Up Night festivities to 6 a.m. Nov. 21 for tightening bolts and placing additional steel supports for the deck.

“The objective is to get as much done as we can this weekend so there’s less to do the second weekend,” Mr. Costa said. “We hope people don’t come to a stop and look at it when they come out of the tunnel on Monday morning and see the bridge is back.”

The bridge deck is scheduled to reopen for traffic in June, but construction is expected to continue on the underside of the bridge and the outbound side of the highway during the summer.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.