Due to a delay in fabricating parts to repair fire damage, the Liberty Bridge’s reopening has been pushed back a week, from Monday until at least Sept. 19.

PennDOT district executive Dan Cessna said Friday that he was disappointed when contractor Joseph B. Fay Co. told him the emergency repair work wouldn’t be completed this weekend. The bridge, which carries 55,000 vehicles a day, has been closed since Sept. 2 after a construction fire warped a 30-foot steel chord that supports tons of weight.

“We just had an unrealistic estimate from the contractor of the time it would take to fabricate the pieces for the repair,” Mr. Cessna said. “We weren’t expecting a delay this lengthy. We’re very disappointed.”

Mr. Cessna said contractors were able to quickly obtain steel for repairs and extra-long bolts from a firm in St. Louis to attach braces. But despite working 24 hours a day, the original fabricator wasn’t able to cut and prepare the steel parts for installation, so Fay has arranged for some of the steel to be shipped to two other fabricators to speed up the process.

Advertise with us

The repairs require 150 pieces of fabricated steel and 400 bolts.

PennDOT and the contractor have worked with engineering consultants and experts from Carnegie Mellon and Lehigh universities to design the repair project. It involves using brackets to bolt 26.5-foot steel pieces on each side and using jacks and possibly heat to stretch the damaged chord, which was compressed 1⅝ inches by the fire.

The fabrication work involves cutting the steel to size, welding pieces together and drilling holes. Under the new schedule, the first parts aren’t expected to arrive until today and the final parts won’t arrive until Tuesday, when crews can begin assembly.

Mr. Cessna said ironworkers who will do the repair work requested a change in the installation of the pieces Friday. Because of the precise nature of the work, ironworkers will drill holes for the bolts at the repair site instead of the fabricator drilling them in advance.

AWK Consulting Engineers of Turtle Creek continues to use a system of lasers and mirrors to monitor any movement of the bridge, which engineers have said was within minutes of collapse had the fire continued. It has moved less than 1,000th of an inch.

Advertise with us

“We’re still very satisfied with the structural integrity of the bridge,” Mr. Cessna said.

The fire began when sparks from a steel-cutting operation ignited plastic ventilation pipe and a tarpaulin, generating more than 1,200 degrees of heat. The federal Occupational Safety and Health Administration is investigating but a final report could take six months.

Fay has an $80 million contract for replacing the deck, painting, installing new signs and rebuilding ramps to the bridge. The company is facing fines of $213,600 a day while the bridge is closed — $8,400 an hour for the unexpected closure of the bridge and $12,000 a day for the closure of the Boulevard of the Allies ramp.

The Port Authority has provided extra service from the South Hills since the bridge has been closed and will continue to do that, spokesman Adam Brandolph said.

The most important aspect is for the bridge to be repaired correctly, Mr. Cessna said.

Advertise with us

“We certainly don’t want to be in this kind of situation,” he said. “Until we can be sure this bridge can be opened safely, it won’t be open.”

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.