For the second time, plans for a switchback ramp from the Smithfield Street Bridge to the Monongahela Wharf trail have been postponed so the project could be redesigned to lower the cost.

The agency Riverlife had expected to begin the project in the spring, but bids for the work came in too high again, said Jay Sukernek, vice president and chief financial officer. Now, it is expected to begin next year.

“We went out to bid and the bids came back higher than the funds at hand,” Mr. Sukernek said. “We had to make a round of tweaks to allow the cost to come down some.”

The agency has a $2.8 million budget for the project including private and philanthropic grants, three state grants totaling $1.5 million and $100,000 from the Allegheny Regional Asset District. Mr. Sukernek said designers made substantial changes to the project last year but this time the “not significant” changes were limited to the foundation for the ramp.

Advertise with us

But because the project involves a historic bridge and sits in a flood plain near an Alcosan trunk line and an interstate highway, any change takes time because it needs to be approved by multiple agencies, Mr. Sukernek said.

Riverlife plans to seek a new round of bids in October and award a contract in early December. That would give the contractor plenty of time to prepare for work during next year’s construction season.

“What we’re trying to do is take away the unknown variables so they can start as soon as possible,” Mr. Sukernek said. “The ultimate goal is to have it done in 2017.”

The 12-foot-wide ramp will begin on the upstream side of the bridge, drop to the east for about 225 feet and make one turn before extending another 450 feet to the wharf. There will be 10 feet of clearance between the railings.

In addition to the ramp, the project will include changes to the 2,017-foot-long trail planting redbud and sycamore trees, a kayak landing and storage facility and a column of riprap along the edge of the river.

Advertise with us

The switchback also has delayed the state Department of Conservation and Natural Resources’ plan for a $1.8 million Point Connect to join the wharf trail with Point State Park. The state wants to do that project, which join the wharf with the Great Allegheny Passage trail, at the same time to avoid multiple disruptions, said Christina Novak, spokeswoman for the agency.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.