A Port Authority contractor began moving barriers Thursday from the far ends of Broadway Avenue in Beechview to the middle section of the street, an indication that replacement of the Red Line tracks for the Light Rail Transit system has reached the halfway point.

Michael Facchiano Contracting Inc. staged the $8.4 million project to complete work in the neighborhood’s business areas first and then work in the more residential middle section between Boustead and Rutherford streets. The business district asked for that approach because owners wanted parking spaces displaced for the shortest time possible.

Work is finished in most of the business district with the exception of an area near the Fallowfield station, where a curve in the track will take longer to replace, said Jim Ritchie, communications director for the transit agency.

The project, which also is being done in one construction season at the neighborhood’s request, is on schedule, Mr. Ritchie said. Facchiano has 180 days to finish the work and could receive financial bonuses for finishing before the Sept. 23 deadline.

Advertise with us

“Overall, it’s going very well,” Mr. Ritchie said. “I’m not going to guess whether they will finish early, but they are not behind schedule at all.”

Pete Wagner, owner of The Huddle bar and restaurant on Broadway, disagreed. He said the agency promised to be finished with work in the business district — and the parking restrictions that come with it — by early July.

“Phase 1 is not complete. The tracks aren’t even in yet,” Mr. Wagner said. “They are moving from in front of our building, which I am happy about, but I’m concerned about the whole business district and they aren’t done when they said they would be done.”

Phyllis Didiano, president of Beechview Area Concerned Citizens, said the project is going much better than the last time the rails were replaced, a two-year project finished in 1998. Some blamed that project with forcing IGA supermarket to close, leaving the neighborhood without a grocery for several years.

“It’s never as good as you’re going to want it to be, but it’s much better than the last time,” she said.

Advertise with us

Ms. Didiano said she feels for business owners because “it’s easy to avoid the area” due to the construction. Residents were thankful for crosswalks created during the construction but were anxious for concrete barriers to be moved Thursday to make businesses more accessible.

“I think the residents are all for the work being done because we know it has to be done, but we try to go to the businesses as much as we can,” she said.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.