Anyone from the South Hills who is headed to the Heinz Field for Saturday’s Kenny Chesney concert should leave early to deal with traffic complications.

The complications include the closure of the Liberty Bridge inbound beginning this evening and the continued closure of West Carson Street on the South Side due to a rock slide.

The inbound Liberty Bridge closure begins at 8 tonight and will last through Sunday morning to allow workers for Joseph B. Fay Co. to prepare for a change in the traffic pattern next week on the bridge, which is undergoing a two-year, $80 million rehabilitation. Once protective barriers are installed and signs and messages boards are changed, the bridge will have one lane open inbound and two lanes outbound until 5 a.m. Tuesday.

West Carson is expected to be closed until at least Wednesday from the Fort Pitt Bridge ramp to Station Square.

Advertise with us

On the Liberty Bridge Tuesday, inbound drivers will find a change in the traffic pattern. They still will be able to use two lanes of traffic, but the lanes will be separated by one lane that is closed for rehabilitation.

PennDOT spokesman Steve Cowan said motorists still will use both lanes of the Liberty Tubes to feed into two lanes on the Liberty Bridge, but the pattern on the bridge will be different. Instead of the far right lane being closed and inbound traffic proceeding on the next two lanes, the far right lane will be open, the next lane closed and the third lane open for inbound traffic.

Traffic patterns still will change three times a day on weekdays with two lanes inbound and one outbound from 5 a.m. to 2 p.m; two adjacent outbound lanes and one inbound lane from 2 to 8 p.m.; and one lane in each direction from 8 p.m. to 5 a.m.

“That’s probably the biggest change drivers will face in this phase: It’s basically the morning rush is going to have two separated lanes on the inbound side,” Mr. Cowan said. “Motorists are going to have to pay attention because it will look a little different.”

Workers are expected to replace the bridge deck in 30 days, then switch to the next lane until all four lanes are finished.

Advertise with us

Another major change could be coming by the end of next week: The ramp from the Liberty Bridge to Boulevard of the Allies and the Parkway East could reopen next Friday.

But that will create another complication for motorists. Anyone wanting to take that ramp will have to use the right lane coming out of the tunnel onto the bridge because there will be no opportunity to change lanes on the bridge due to construction between the two lanes.

Mr. Cowan said such changes will occur regularly during the two-year, $80 million project.

“Motorists will need to adapt and adjust every 30 or 40 days,” he said. “Just as motorists get used to the traffic pattern, it will change again.”

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.