The first weekend closure of the Parkway East last weekend didn’t get off to a rousing start and some minor tweaks are planned for the second closure next weekend, but Pittsburgh officials remain confident that preparations to demolish the Greenfield Bridge during the week after Christmas are on schedule.

Pittsburgh officials had wanted to close the Parkway East around Squirrel Hill from 11 p.m. last Friday through early Monday morning so crews from Mosites Heavy Construction could begin removing the road surface safely from the bridge above the highway. The preparation work must be completed during the two weekend closures so demolition can be done between Christmas and New Year’s Day — the least busy days of the year for parkway traffic — or state officials won’t allow the highway to be closed again until the same period next year.

But an accident on the highway delayed the start of work until about 1 a.m. Saturday, said Pat Hassett, assistant public works director overseeing the project. An early rainstorm Sunday morning also delayed work, he said.

“They didn’t get as much done as they wanted, but they did enough,” Mr. Hassett said. “We’ve got a good team there in Mosites Heavy Construction.”

Advertise with us

Mr. Hassett said crews had to deal with a half-dozen drivers who went around barricades to get on the closed parkway. In one instance, he said, a truck driver entered the parkway at Squirrel Hill going outbound, which was open, but realized he wanted to go inbound and made a U-turn after exiting the Squirrel Hill Tunnel and headed inbound on a section of the highway that was closed.

Officials stopped all of the errant drivers and no one was injured.

The traffic detours the city put in place worked reasonably well, Mr. Hassett said. That included a late decision to allow local inbound traffic to continue to Swissvale rather than making everyone exit at Wilkinsburg/​Forest Hills, which was the recommended detour.

The change allowed motorists who lived in the Regent Square area to get off there. Some additional traffic likely stayed on the highway to Swissvale, Mr. Hassett said, but those motorists probably got stuck in more traffic than they would have had they followed the recommended detour, so they aren’t likely to do that again.

“The detours worked pretty well. We expected people to find alternative routes [other than the official detour] and they did,” he said.

Advertise with us

“That’s not to say it didn’t hurt — it certainly did — but given the magnitude of the detour and the number of vehicles involved, I don’t think it was too bad.”

For the second closure scheduled to begin at 10 p.m. next Friday, Mr. Hassett said, the detour routes will remain the same but work will finish by 5 p.m. Dec. 6 due to the Steelers home game at 8:30 that night. Public works officials will meet with police this week to decide whether 21 officers assigned to help move traffic are deployed correctly or should be moved to other intersections.

During the week after Christmas, the highway is scheduled to be closed for four days while crews truck in dirt to create a dirt pillow under the bridge, implode it and haul away the debris and dirt.

The Greenfield Bridge closed Oct. 18 for a $17.5 million replacement project that is expected to take about 18 months.

Ed Blazina: eblazina@post-gazette.com