The outbound Parkway West will close overnight at 10 p.m. from Green Tree-Crafton to Interstate 79, the first of four overnight closures scheduled this week as a $72.8 million reconstruction project continues.

Inbound traffic will be reduced to one lane at the same time. All restrictions will be removed by 6 a.m. Tuesday.

PennDOT announced this schedule for the rest of the week:

• Tuesday and Wednesday: Full inbound closure from I-79 to Parkway Center starting at 10 p.m. from I-79 to Parkway Center; single-lane traffic outbound starting one hour after the Pirate game ends. Restrictions lifted by 6 a.m. daily.

Advertise with us

• Thursday: Full closure outbound from Green Tree-Crafton to I-79 and single-lane traffic inbound starting at 10 p.m. and ending by 6 a.m. Friday.

Jon Schmitz: jschmitz@post-gazette.com.