When the McElheny Road Bridge reopened Monday after an eight-month closure for repairs, there was no fanfare.

There were, however, sighs of relief from local residents, business owners and motorists no longer inconvenienced by construction detours for the nearly $200,000 renovation project.

Traversed by thousands of vehicles each week, McElheny Road Bridge is a small but significant structure that is a dividing line for Jefferson Hills and South Park Township. The towns jointly own the bridge.

South Park Township manager Karen Fosbaugh called the bridge project “a good example of how two governments can work well together” for the betterment of their communities.

Advertise with us

“You always hear about gridlocks and a lot of negativity in government, and I think it’s important that the public know that that’s not always the case. There are instances, like this, when elected bodies can work well together and move forward,” she said.

Jefferson Hills manager Douglas C. Arndt could not be reached for comment.

The $193,136 total project cost included a $153,108 base bid, awarded to Lone Pine Construction Inc. of Bentleyville, plus $40,028 in change orders, Ms. Fosbaugh said. Expenses for both towns were offset by a $100,000 grant from the Allegheny County Department of Economic Development’s Community Infrastructure and Tourism Fund. The $93,136 balance was split 50/50, with each town paying $46,568, she said.

The township paid its share through its capital expenditures fund, and the borough used its general budget.

In addition to routine traffic, police, fire and ambulances in both towns use the bridge frequently, especially to assist neighboring units. Also, employees of the 200-acre Bruceton Research Center travel the bridge daily to access secondary entrances to the federal facilities there, Ms. Fosbaugh said.

Advertise with us

The Pennsylvania Department of Transportation and project engineers inspected the bridge Monday morning; it reopened that afternoon.

It was a 2013 PennDOT engineering report that led both governing bodies to take action, Ms. Fosbaugh said. The report noted that the structure had deteriorated to the point that repairs were critical; the bridge faced permanent closing in 2014 if deficiencies were not addressed, she said. Closure would affect the health, safety and welfare of many residents in both towns, she said.

On May 13, 2013, the township board of supervisors and borough council signed a memorandum of understanding regarding expenses and other issues. Construction began on Sept. 8, 2014.

The two-lane, concrete deck bridge, which intersects Cochrans Mill Road on the Jefferson Hills side, and McElheny Road on the South Park Township side, is 30 feet, 6 inches long by 23 feet, 4 inches wide, with no weight restrictions.

The renovation included replacing the bridge decking and beams, repairing head walls on both sides, installing new guide rails, and paving areas adjacent to the bridge with asphalt, said project managers Tom Lovell, for Jefferson Hills, and Bruce Beaver, for South Park Township. It is thought to be the first major upgrade that McElheny Road Bridge has had since it was constructed in 1970 to replace a single-lane structure made of stone, they said.

Advertise with us

Previous annual PennDOT inspection reports indicated that the bridge had been deteriorating for the past 15 years. For at least the past three years, traffic was restricted to one lane with a 3-ton limit, Mr. Beaver said.

During construction, some residents and motorists experienced “a double whammy” of detour inconveniences, Mr. Beaver said. The bridge project began around the same time as a PennDOT project that closed a portion of Cochrans Mill Road over the winter months. That project involved rebuilding a washed-out roadway that was next to a creek, he said.

There also were times when police, ambulance and fire truck response times were impeded, especially when assisting other units, the project managers said. Emergency vehicles had to drive several miles out of their way via detours to get to an emergency site.

Routine project “hiccups” along the way included: materials missed in initial ordering; winter weather delays; stream bank stabilization issues; and a longer wait time for fabrication of a new type of guide rail because PennDOT changed specifications mid-project, the project managers said.

“The project definitely was an inconvenience for everyone, but everything seemed to go fairly smoothly. The borough and township have a great working relationship with each other,” Mr. Lovell said.