Replacement of the deteriorated Kenmawr Bridge connecting Rankin and Swissvale will require construction of two bridges, according to plans unveiled last week by the Pennsylvania Department of Transportation.
Because it wants to build the new bridge in the current alignment, PennDOT will build a temporary span just west of the existing structure to carry traffic for the expected five-month construction period, said Dan Cessna, district executive. Detouring traffic on busy South Braddock Avenue for the entire project wasn’t considered feasible.
The temporary bridge will have a steep grade and 20 mph speed limit, said William Siess, project manager for SAI Consulting Engineers, which is designing the new structure.
PennDOT is hoping to build the new bridge in one construction season in 2017, he said. Brief detours will be required at the start of the project and a one-month detour is likely while the road connections to the new bridge are built.
The project is more challenging than typical bridge construction because of the need to build the new bridge 3 feet higher over the Norfolk Southern railroad tracks that pass under it, Mr. Siess said. That will provide sufficient clearance when the railroad begins operating double-stack freight trains in the corridor.
The new bridge also is designed to accommodate an extension of Port Authority’s Martin Luther King Jr. East Busway if the authority ever decides to extend it.
“Generally, it is an item of interest so we’re very appreciative that we were able to work with PennDOT to include this possibility in its bridge design,” authority spokesman Jim Ritchie said.
The new bridge will be 121 feet long (the current structure is 73 feet long) and have two extra-wide 14-foot travel lanes. Sidewalks on both sides will be about 6 feet wide, Mr. Siess said. Approaches on both sides will be reconstructed, providing new pavement from Hawkins Village to Woodstock Avenue. Several side streets in the construction zone will be improved.
The current structure is 105 years old and deteriorated to the point that it carries a 6-ton weight limit, making it off-limits to anything heavier than a delivery van.
Port Authority has detoured its buses on four routes -- P7 McKeesport Flyer, 59 Mon Valley, P71 Swisshelm Park-Rankin Flyer and 71 Edgewood Towne Centre — around the bridge since early 2013 and is likely to continue doing so until the new bridge opens.
Norfolk Southern currently is making repairs to the bridge that should enable the weight limit to be raised to 12 tons, Mr. Cessna said. That is not sufficient to allow buses on it.
The $11.75 million replacement project also will clarify the fragmented ownership of the bridge, for which two municipalities and the railroad currently have responsibilities. Allegheny County will own the new bridge.
The project is 80 percent federally funded. The state and railroad each will pay about 10 percent of the cost.
Jon Schmitz: jschmitz@post-gazette.com or 412-263-1868. Twitter: @pgtraffic.