A new traffic pattern is scheduled to take effect for the $28.5 million Birmingham Bridge rehabilitation project on Monday morning rather than Friday night, the Pennsylvania Department of Transportation announced.

Restrictions began last Monday in preparation for the traffic shifts, which will affect motorists and bicyclists, PennDOT said.

Northbound traffic toward Oakland will be restricted to a single lane at the bridge approach through Friday. Two southbound lanes toward the South Side will be closed through Friday. The southbound shoulder has been closed all week and bicyclists should use the other side.

Pittsburgh police will direct traffic from 3 p.m. to 7 p.m. daily this week.

Advertise with us

At 5 a.m. Monday, the northbound side of the bridge will close and traffic will be shifted to the southbound lanes. There will be one 12-foot-wide northbound lane, two 12-foot-wide southbound lanes and a bike lane. Pedestrians will be directed to use the sidewalk on the southbound side.

The northbound ramp to Forbes Avenue and Oakland will close, and motorists and cyclists will be detoured.

Vehicles will continue past the ramp to Fifth Avenue and turn left there and again at Moultrie Street to reach Forbes. Bicyclists will use the two-way bike lane on the ramp to a right on Forbes, left on Craft and left on Fifth Avenue.

Left turns by bicyclists from Fifth Avenue to the southbound bridge approach will be prohibited. They will continue inbound to a left on Moultrie and left on Forbes to reach the bridge approach.

The revised traffic patterns will be in place around the clock through Nov. 11, according to the schedule.

The overall project, which includes painting of the superstructure, steel and substructure repairs, bearing replacements, new light poles and resurfacing, will continue into the spring of 2017.