For the second time this month, PennDOT has postponed a planned closure of the inbound Fort Pitt Tunnel because of the weather.

A snowy weekend forecast wiped out the latest closure, planned for 10 p.m. Friday, spokesman Steve Cowan said. The closure will be rescheduled.

PennDOT also announced that an inbound lane of the tunnel will be closed nightly starting Monday and continuing through the end of the year.

The restrictions will be in place from 10 p.m. to 6 a.m. weekdays through Dec. 30 as a $14.2 million project to remove the tunnel ceiling continues.

Advertise with us

Outbound overnight lane closures are expected to begin in March.

PennDOT had hoped to have another go at closing the inbound tunnel this weekend to continue to remove the tunnel ceiling.

Two full weekend closures of the outbound tunnel are likely in February and March, Mr. Cowan said. One more full weekend closure on the inbound side is planned this year in addition to the one postponed on Friday.

Also, there will be four weekends with nighttime full tunnel closures. Dates and times have not been set.