The Monongahela Incline will be closed for up to 70 days this fall during a $3.5 million project to replace rails and ties and make other improvements.
A Port Authority committee on Thursday approved a contract with Mosites Construction Co. for the work, described by Keith Wargo, authority assistant general manager, as “a major rehabilitation.”
The exact date of the shutdown hasn’t been determined. The schedule is designed to avoid the peak usage months of June through August while giving the contractor time to complete work before winter, Mr. Wargo said. Buses will operate between the stations during the closure.
The agency is hoping the closure will be shorter than 70 days, he said.
The full authority board is scheduled to vote on the contract next Friday.