Nearly 17 months after a fire tore through the Elizabeth Forward High School auditorium, district leaders are taking some of their first steps to rebuild parts of the 67-year-old building.
School directors last week unanimously approved five construction contracts, which will allow the project to get underway in the coming months. Work will largely focus on a new auditorium and gymnasium. The project was recently expanded to include a new HVAC system to give the school air conditioning, something it did not previously have.
The project will total $52.9 million, an increase from early estimates that hovered around $27 million. It is part of a multi-phased approach that could eventually lead to the reconfiguration of school buildings and consolidation of three elementary schools.
“We’re excited to put EF in a better position for the next 50 years,” school board President Thomas Sharkey told the Post-Gazette this week. “I grew up here, I graduated from EF in ‘93. Ever since I’ve been on the board it’s always been my goal to move the community forward. … I believe at the end when we’re done with this whole project, not just this part, that the community as a whole and the students we serve will be in a better place.”
Renovation plans come after a Feb. 12, 2023 fire ravaged the school’s auditorium and stage. The lobby, music wing and several hallways leading to the media center — areas near the auditorium — had water damage, and smoke impacted the entire building.
Because of the damage, students were forced into online learning. During that time crews demolished part of the auditorium to access a mechanical room that was key to getting the school up and running. When students returned to in-person learning, rooms and areas adjacent to the auditorium were walled off so they could not be accessed. Accessible areas of the building were cleaned and daily air quality testing at the time yielded healthy results.
Read More
Superintendent Keith Konyk said the Allegheny County Fire Marshal was not able to determine a cause for the fire, but they did rule out any electrical issues.
Work to repair that damage will now start this fall after school directors approved new contracts.
Those include a $38.7 million contract with Lawrenceville-based Rycon Construction for general construction services; a $1.8 million contract with Avalon-based First American Industries for plumbing; an almost $1.7 million contract with West Deer-based Vrabel Plumbing for school fire protection; a $3.8 million contract with Lincoln-based Moses Electric for electrical services; and a $6.7 million contract with Thornburg-based Lugaila Mechanical for HVAC upgrades.
In all, the project will include new spaces such as an auditorium, a band and choral room, a main entrance with captive security, a lobby, gymnasium and locker rooms.
The new auditorium will be constructed on the side of the school closest to Weigles Hill Road, which is opposite from its current location. The auditorium, which will feature its own outside entrance, will hold close to 1,000 people, an increase from the old space, which had capacity for 725.
The gymnasium, with capacity for 1,200 people, will be built where the current auditorium sits. It will be connected to the school’s main entrance and lobby, which will have improved security systems such as a secure vestibule and automated systems for checking guests’ IDs. The old gym will be used as an auxiliary space.
A physical plant for the school’s mechanical, electrical and plumbing systems will be built underneath the new gym. That boiler room, Mr. Konyk said, is where officials saw an opportunity to expand the project to include air conditioning and new ventilation and air filtration systems.
“This is actually a more responsible and efficient way to do things instead of having it broken up into parts,” Mr. Konyk said. “You bring these folks in and they do everything at once.”
In addition to the $52.9 million in construction costs for the first phase of the project, the district also earmarked an additional $14.5 million for project contingencies, new furniture, audiovisual equipment, IT infrastructure, permits, fees and inspections.
The district plans to use insurance money and bonds to pay for the first phase of construction. They are also applying for grants.
Officials are now planning to break ground in September on the gymnasium and mechanical room, expected to be completed next fall. The auditorium will be done by summer 2026. Minimal disruptions are expected for students, Mr. Konyk said.
In addition to the first phase of projects, district leaders are planning a second phase that includes an expansion of classrooms at the back of the high school.
That space would be used under proposed consolidation plans presented this spring.
Under the proposal, three elementary schools — Greenock, Mt. Vernon and William Penn — would close. From there, kindergartners and first graders would attend the current Central Elementary. Those in second through sixth grade would move into the middle school, and seventh and eighth graders would be relocated into the new wing of the high school.
“Now that we have the contracts awarded … we really see an opportunity now to really look at phase two and have those conversations with our school board and figure out exactly what that looks like,” Mr. Konyk said.
But for now, district officials are excited for the future of the high school.
“This is going to be something that’s going to change the district and really prepare for the next 30, 40 or even 50 years,” Mr. Konyk said. “We’re sad that it took a fire to get here but we’re incredibly excited that we’re going to be part of changing this district forever.”