Repairs and safety checks now completed and a lawsuit resolved, a five-level parking garage at California University of Pennsylvania is back in use as of Monday, five years after a partial ceiling collapse forced its closure.
The 650-space Vulcan Garage located behind the campus library "has been inspected, tested and deemed safe for use, ” Fawn Petrosky, vice president for finance at Cal U, said in a statement.
The $13 million garage initially opened in 2010 but was closed as a precaution after a 20- by 2-foot piece of concrete on the facility’s second level broke off and fell to the ground level on Aug. 26, 2016 as students on campus were beginning to arrive for fall move-in. There were no injuries and no cars were damaged, but campus officials said a subsequent inspection found additional safety hazards.
Cal U was largely mum on the collapse and possible causes in the months afterward. But surveillance video capturing the failure, as well as photos and internal correspondence were turned over to the Pittsburgh Post-Gazette after a year-long public records fight showed Cal U’s scramble for answers.
Surveillance video: Vulcan garage deck collapses
In 2018, Cal U sued the contractor Manheim Corp. and its bond-holder, Travelers Casualty and Surety Co. of America. A settlement was reached in 2020 under which Cal U officials were to receive nearly $4 million to cover repair costs and other expenses, including lost parking revenue.
Cal U officials said that under the agreement, repairs were funded entirely by the defendants.
Read More
On Monday, the first trickle of cars arrived after 7 a.m.
“I’m told that some students and employees already have reached out, and that a handful of “drive in” folks (paying by the day) have arrived already,” Cal U spokeswoman Christine Kindl said at midmorning. “We have a managed parking system that requires a permit for a specific lot, so students and employees wishing to make the garage their permanent parking spot must work with Parking & Transportation to be assigned a space.”
Contractor Howard Shockey and Sons Inc. performed the repairs, which included inspecting and rewelding key connections, and fortifying beams with additional rebar to add strength, campus officials said.
The garage and a nearby convocation center were developed during a building and enrollment boom at Cal U and other universities of the State System of Higher Education that peaked in 2010. Since then, Cal U’s enrollment has declined by 31% from 9,400 to 6,512 students as of this fall.
Ms. Kindl said that “although our enrollment has changed since the garage was closed, we expect to use the facility for event and visitor parking, in addition to parking for students and employees.”
In its statement announcing the reopening, Cal U officials said Global engineering firm Wiss, Janney, Elstner Associates (WJE) and independent testing agency Construction Engineering Consultants Inc. “performed inspections and testing during all phases of the repair work. The state Department of Labor and Industry also inspected the garage and issued an occupancy permit.”
Officials welcomed the garage’s return, among them Ms. Petrosky.
“Bringing this parking structure safely back online provides greater flexibility not only for day- to-day parking needs, but also for special events that bring families and other visitors to campus,” she said
Bill Schackner: bschackner@post-gazette.com, 412-263-1977 and on Twitter: @Bschackner