The construction of a $100 million high school in the West Jefferson Hills School District is back on track after Commonwealth Court ruled last week that a plumber delayed the work unnecessarily.
Wheels Mechanical Contracting, which last year was awarded the contract to construct all the water and sewer lines within the high school and up to 5 feet outside the building, took the school district to court in June, arguing that it also should have been responsible for the pipes outside the building. A trial court initially agreed with the plumbing company and temporarily halted some of the construction, arguing that the Pennsylvania School Code requires that all plumbing work be done by a plumbing contractor. That decision was overturned Feb. 28 by a Commonwealth Court decision, which said Wheels should have made the argument sooner, rather than waiting until construction was underway.
“The important thing is we can now proceed full speed ahead as we get into the construction season,” said Robert McTiernan, solicitor for the school district.
The school board awarded Wheels a $4.6 million contract in January 2016. Nello Construction, the general contractor, was awarded a $42 million contract to do the majority of the construction, including the plumbing work outside the school building. Wheels filed its suit in June, asking for a temporary injunction to stop the work that was already underway.
“Wheels was well aware when it submitted its bid that the disputed work was part of the general construction contract and not part of the plumbing contract,” according to the Commonwealth Court ruling. “Yet, Wheels failed to exercise due diligence by waiting months after construction was underway to institute the action.”
Wheels argued in court that the construction was not underway at the time of the injunction, but Commonwealth Court found that materials were purchased and delivered by the time Wheels filed in court, and at the time of the injunction in October, a significant amount of work on the sewer and water lines had already been completed.
“It was much more of an interference with the successful completion of the project than was let on to the lower court,” Mr. McTiernan said.
Work has now resumed, with Wheels and Nello completing the work they were each contracted to do. The high school is expected to be completed in 2018.
Elizabeth Behrman: Lbehrman@post-gazette.com or 412-263-1590.