The North Allegheny School District will look to tech companies and foundations for help in paying for a digital media center at the intermediate high school.
The school board previously was presented with three clusters of renovations at the 62-year-old building. Two of the clusters are typical renovations, including upgrading the auditorium, renovating the biology lab and replacing the heating and air conditioning.
But the third cluster involved converting an unused courtyard into a digital media center for $3.1 million. Although some board members are in favor of doing that, the majority of members are leery of amount of additional debt.
“We have to be careful about how much debt we take on,” board president Tara Fisher said at the Aug. 24 meeting, noting that the project would add $120,000 a year to the district’s budget. “That is two to three teachers at secondary level that we could not hire. The board needs to weigh all of that information in making those decisions.”
Mrs. Fisher added that the board has contacted the North Allegheny Foundation for help in securing the money for the digital center.
“We know that there is money out there. We know that there are many Pittsburgh-based technology companies. Part of this is exhausting alternative revenue sources first before we hit the district budget.”
The original cost of the other clusters was estimated at $5.3 million. But the board approved a fee to Apostolou Associates Inc., the architect on the project, for $100,924 to prepare plans for an additional $1.1 million in work at the building.
In other action, the board approved a $132,140 contract with R.A. Glandy and Sons Inc. for window repairs at McKnight Elementary School to stop leaks.
Also at its Aug. 24 meeting, the school board heard from administrators about possible delays for buses due to the closure of a portion of Pine Creek Road at Route 19.
Roger Botti, director of transportation and operations, said the district asked McCandless police to manually run the traffic signals at Route 19 and Ingomar Road, the official detour, to ease traffic backups. Classes began Thursday in the district.
Sandy Trozzo, freelance writer: suburbanliving@post-gazette.com




Comments