With less than a week to go before students were to return to classes, Moon Area school directors have decided to delay the start of school to give construction crews additional time at J.A. Allard and J. H. Brooks elementary schools.
The divided board voted late Monday night to change the first day of school from Monday to Aug. 24 for all 3,700 Crescent and Moon students.
Directors repeatedly stated they were not concerned with safety because the buildings would not be provided occupancy permits if safety was an issue. The decision was made, they said, to provide a better learning environment for students.
Directors Scott LaRue, A. Michael Olszewski, Laura Schisler and Samuel Tranter voted against postponing the start date. Mr. Tranter had suggested the district wait until after Labor Day. A two-week delay also was considered.
The decision was made the day after directors were given tours by superintendent Curt Baker of the two construction sites and the Richard J. Hyde Educational Resource Center, where work is being completed to create a central kitchen.
With the closing of Hyde Elementary School, the elementary grade configuration has been changed from five schools of grades K-4 to four schools — K-2 students in Brooks and Bon Meade elementaries and grades 3-4 in McCormick and Allard.
Prior to the start of the director’s tour at Allard, a handful of parents confronted Mr. Baker about safety, building conditions and the ultimate completion dates for the projects, which began prior to the end of last school year.
Parents also said they were unhappy about a 10-day notice from the district informing them that the first day of school would be an orientation day where students and their parents would be bused from the Kmart shopping center on Beaver Grade Road to the four elementary schools to tour classrooms and meet teachers.
Mr. Baker said Sunday that Allard and Brooks would be “at substantial completion” by the time school bells were to ring Monday.
A district communication said “substantial completion means construction will be at the point where teachers and students can safely occupy the building. Classrooms will be intact and fully operable for instruction — this includes all fixtures, furnishings and supplies necessary for instruction. Both schools will have safe entry and exit points. All safety systems will be fully functional.”
As of Sunday afternoon, some classrooms at Allard were being cleaned in preparation for teachers to occupy them. Other classrooms were still missing ceiling tiles, doors or other fixtures.
At Brooks, kindergarten and first-grade classrooms were awaiting installation of sinks and toilets as well as ceiling tiles and other finishing touches.
Hallway ceiling tiles at both schools had yet to be installed. Flooring was not yet complete in all areas.
“It’s a lot, but everybody is on board. It’s not like [the contractors and administration] haven’t talked daily,” Margaret Lindsey, chief operating officer and chief financial officer for the district, said Sunday. “We meet as a group every Wednesday.”
Mrs. Lindsey said she expected to see about 100 workers daily at each school in preparation for the final push and placing the finishing touches on classrooms, hallways and open-concept imagination spaces that incorporate lifelike tree sculptures and sunshine tunnels.
Doors will be hung, paint touched up and installation of classroom cubbies at Brooks and lockers at Allard will be completed. The kitchen appliances are to be installed at Hyde, too.
As of Monday evening, desks were being moved into a few of the classrooms and the local fire chief had been on site to inspect the schools.
“Literally, everything is new. It’s turned itself from a 1960s building to a 2015 building,” Mr. Baker said of the revamped Allard structure, which was built in 1968. “We honor its original construction and effectively turn it into a new building.”
A total of 8,000 square feet was added to Allard including a new gymnasium separate from the cafeteria and a library allowing for natural lighting.
Mr. Baker expects a “vast majority” of any remaining interior and building work at both sites to be completed in September, with exterior work carrying over into October. Director Denny Harbaugh Jr., who said he has visited the construction sites on a weekly basis throughout the project, gave a projected end date of Oct. 15.
Even with the one-week extension, portions of both schools will not be completed in time for the start of classes and will be blocked from student access. Work in most spaces will finish within a few days of school beginning. The gymnasiums and cafeterias may not be available for another week.
Students will be served bagged “alternative lunches” similar to what was provided in May when cafeterias were closed in preparation for transformation into warming kitchens.
With school in session, construction work won’t start until 4 p.m.