Parents, staff and students who enter through the front of Fox Chapel Area High School on the first day of classes on Sept. 2 will come through a new, two-story secure vestibule.

The atrium-style entrance is being constructed to enhance security.

“As has been the policy for the last several years,” said Bonnie Berzonski, coordinator of communications for the district, “members of the high school office staff willl be able to see who is waiting to enter the building and then allow them to enter only after verifying their identity.”

Part of the reason the school board voted to start the 2015-2016 school year a few days later than normal was so that as much of the $34 million construction project, which began last year and will continue through at least part of this year, could be completed before the first day, according to Ms. Berzonski.

Advertise with us

In addition to the new entrance, students will be using refurbished restrooms, a project that began last year.

Breakfast and lunch will be served from a brand new kitchen, locker rooms have been updated and the lockers for student belongings will be new. All classrooms will be entered through new, locking doors.

“We are working to have everything ready as close to the beginning of the school year as possible,” Ms. Berzonski said.

The largest project, a new addition to the gymnasium wing for a natatorium, should be completed sometime in November or December, according to Ms. Berzonski.

The contactors are completing the installation of the steel supports for the addition and the bleachers are in place.

Advertise with us

“We are really excited about the new opportunities that these renovations and additions will provide to our students and the community,” said Ms. Berzonski. “We know that these improvements to the high school facility will benefit students from across the district for many years to come.”

Rita Michel, freelance writer, suburbanliving@post-gazette.com.