Commercial Street in Frick Park under the Parkway East will close for about 10 hours on Thursday while contractors test whether their system to move a new bridge will work.

The closure, which begins at 6 a.m., is a key step in the replacement of the Commercial Street Bridge located just outside the outbound Squirrel Hill Tunnel. S&B Fay USA has spent the past 18 months building the new bridge beside the current one and plans to move the new structure into place next month, so subcontractor Mammoet will test the moving system during the closure Thursday.

The Netherlands-based company plans to move the new bridge about a foot during the test just to make sure the process will work as planned.

As a result, Commercial Street will be closed to vehicles from Whipple Street to Summerset Drive, and the Nine Mile Run Trail will be closed to pedestrians and bicyclists between the Nine Mile Run parking lot in Swisshelm Park and the Frick Park Commercial Street parking lot in Squirrel Hill.

Advertise with us

For the real move, Mammoet will use 42 hydraulic jacks to move the new bridge about 102 feet so it can be attached to the existing abutments at each end of the bridge. It will give the system a test run during the Thursday closure to make sure it will move the bridge that is 846 feet long and weighs 22 million pounds.

For travelers coming from Swisshelm Park toward Pittsburgh, the detour will require a turn onto Whipple Street, left onto Monongahela Avenue, left on South Braddock Avenue, left onto Forbes and left on Beechwood Boulevard. The detour is the reverse for outbound traffic.

The test is the preliminary for the big effort that begins at the end of the month. Commercial Street and the trail will close in the same area from June 29 through early August for preliminary work and cleanup after the new bridge is in place.

A car passes on Commercial Street as construction workers work on the surface of the Commercial Street Bridge replacement Wednesday, June 24, 2026, in Swisshelm Park. (Alexandra Wimley / Pittsburgh Post-Gazette)

The highway itself will close for 25 days beginning July 10, leaving about 100,000 motorists a day looking for alternative routes. PennDOT has recommended detour routes on its website.

During the closure, demolition experts first will take the deck off the old bridge with machines, then explosives will be used to knock down the superstructure. After some cleanup, Mammoet will slowly move the new bridge in place at about a foot an hour, then it will be attached and highway approaches will be completed by Aug. 3, if everything goes according to schedule.

The contractor has financial incentives to get the work done early and faces penalties if it is late.