The Chartiers Valley School District administration presented a proposed five-year capital improvement plan for the district at a recent meeting.

The plan, presented by district superintendent Johannah Vanatta at an Oct. 12 meeting, addressed both finishing up areas at the secondary school campus that were not addressed during the recent high school/middle school reconstruction project as well as plans for other facilities throughout the district.

Currently, the district is in the midst of post-construction at the high school and addressing needs at the intermediate school. In 2022, the district will focus on the primary school, roofing and heating, ventilating and air conditioning systems. In 2022-23, the secondary campus will be addressed with maintenance on the gym, gym lobby, auditorium rigging and curtains, the pool and locker room area and the track and stadium areas and baseball field.

In years 2023-26 the district would like to address projects at the intermediate school including roofing, the HVAC system, and interior and exterior renovations.

Advertise with us

After 2026, the district plans to evaluate how successful the process was.

If the projects are approved by the board, funding would come from various sources.

For the current high school post-construction costs which include the roofing and HVAC system, the projected cost for the HVAC would be around $95,550 and the roof around $2.3 million. For the HVAC system, approximately $63,680 would be funded from the district’s capital budget and $31,870 from the Elementary and Secondary School Emergency Relief Fund.

At the primary school, the improvements would cost around $3.8 million, with about $2 million from Elementary and Secondary School Emergency Relief Funds and $1.8 million from a bond.

Costs for the secondary campus improvements would be around $17 million and would come from a bond. The estimated cost of the improvements to the intermediate school campus would be $30 million and would come from a bond.

Advertise with us

The next step for years one to three of the project is for the district and board to analyze its fiscal information and convene a bond agent to prepare finance documents. A presentation, request for proposals and information will likely be presented to the board in November.