Baseball fans from the region’s western locations endured up to 90 minutes in bumper-to-bumper traffic Sunday on a detour around the inbound Parkway West.
Maybe the traffic was lighter, or maybe they planned ahead, but either way they seem to have fared better than the others who drove in for the earlier Pirates games in this weekend’s series.
Steve Cowan, press officer for the Pennsylvania Department of Transportation, said the detour took upward of three hours to travel Saturday afternoon and evening. And about an hour after the end of Friday night’s game, traffic was restricted to a single lane from the Fort Pitt Tunnel through the Banksville interchange on the Parkway West outbound, and all drivers were forced to get off at that junction.
“I would imagine that many individuals heading into Pittsburgh probably saw the significant delays, particularly Saturday, and made some decisions to use alternate routes,” Mr. Cowan said.
The Parkway West is undergoing an over-$70 million improvement project that is requiring intermittent shutdowns, one of which occurred this weekend.
On the inbound side of things, beginning about 9 p.m. Friday, the Parkway West was shut down from Interstate 79 to the Fort Pitt Tunnel. On Sunday evening, the parkway, including the tunnel, reopened from Parkway Center Drive and Banksville Road.
Mr. Cowan said there’s a chance of an earlier-than-scheduled (6 a.m.) full reopening, possible late Sunday. But, no guarantees.
Fans leaving Sunday’s Pirates game were greeted by only the normal frustration that comes with getting out of the city after the game: The Parkway West outbound work finished ahead of scheduled at about 11:45 a.m. Sunday, about five hours before it was scheduled to be completed. In the end, congestion issues have plagued both directions of the parkway, Mr. Cowan said.
The Parkway West project extends through December and will entail multiple weekend closures. Work includes milling and repaving the 5.5 miles between Interstate 79 and the tunnels, reconstructing all shoulders, rehabilitating several bridges and overhead sign structures, and replacing center median barriers.
Mr. Cowan acknowledged the inconvenience of what he described as a “long, circuitous detour route” through Carnegie and Green Tree into the West End, then onto West Carson Street.
“We try to limit our impact on major event days. However, this work is extremely important and there’s no way to do this work without a closure. We don’t want to inconvenience motorists, but it’s essential that we get this work complete,” he said.
Karen Kane: kkane@post-gazette.com or at 724-772-9180. Molly Born: mborn@post-gazette.com or 412-263-1944.