Ten months of hassles for Parkway West drivers will begin tonight, when the Pennsylvania Department of Transportation will close the on- and off-ramps at Carnegie.

The ramps will be closed at 10 p.m. and remain closed through late December for the second year of a $72.8 million parkway reconstruction project that will stretch from Interstate 79 to the Fort Pitt Tunnel.

Also, traffic on the parkway will be restricted to a single lane in both directions between I-79 and Parkway Center after 10 p.m. Monday through Thursday. Restrictions will be lifted by 6 a.m. each day. The lane closures are needed while crews set up the work zones.

The project will cause a variety of traffic shifts, narrowed lanes, lane closures and full overnight and weekend detours as the contractor, Swank Construction Co. of New Kensington, moves from I-79 toward the tunnels.

Advertise with us

The mainline project is one of three underway, including construction of a fourth outbound lane from Rosslyn Farms through the I-79 interchange and removal of the ceilings in the Fort Pitt Tunnel.

Six full weekend closures — three in each direction — will be needed during parkway resurfacing, the first coming in late April or early May on the outbound parkway from Rosslyn Farms to I-79.

On four other weekends, traffic will be restricted to a single lane from Friday night to Monday morning to allow work on 15 bridges and three culverts. Dates have not been announced.

Ramps at Banksville Road and Parkway Center will have full weekend closures at dates to be announced. The ramp from Poplar Street in Green Tree to the outbound parkway will be closed for a 30-day span, probably in late April or early May, and the Poplar ramp to the inbound parkway will close nightly.

Work on three bridges at the Carnegie interchange will shift all traffic to the inbound side initially, then to the outbound side as the project progresses. The bridges cross the West Busway, Chartiers Creek and Whiskey Run near the railroad overpass.

Advertise with us

West of the bridges, traffic will be shifted toward the shoulders that were rebuilt last summer to allow work on the center median barrier. East of the bridges, work will begin on the shoulders, pinching traffic toward the center.

Lanes will be narrow and walled in by concrete barriers as they were last year, and the speed limit will be reduced to 45 mph.

The posted detours for the Carnegie interchange are:

• Inbound off-ramp — Exit at I-79 south to Exit 57 (Carnegie); left at West Main Street. Or exit at Green Tree (Exit 67); left at Greentree Road; left on Mansfield Avenue; left on Noblestown Road, which becomes East Main Street.

• Outbound off-ramp — Exit at Green Tree; bear left at Route 121 toward Crafton; left at Mansfield Avenue; left on Noblestown Road, which becomes East Main Street. Or continue to I-79 south, exiting at Carnegie and left at West Main.

Advertise with us

• Inbound on-ramp — Use Chestnut Street to right on East Main, which becomes Noblestown Road; right at Mansfield Avenue which becomes Route 121; left at Greentree Road; right at Parkway Center Drive.

• Outbound on-ramp — Use Chestnut Street to left at Mansfield Boulevard, which becomes West Main; left at I-79 northbound ramp; I-79 to Parkway West interchange.

Also beginning tonight are overnight single-lane closures in the inbound Fort Pitt Tunnel, which will continue on weeknights through the end of the year.

Single-lane traffic will begin at 10 p.m. daily and end by 6 a.m. Outbound nighttime lane closures are scheduled to begin in late March.