Winter weather wasn't enough to keep about 20 Carnegie area residents away from a public Parkway West improvement project session Feb.12, with representatives from the Pennsylvania Department of Transportation Department and its contractor, Swank Construction.

The $72.8 million project, which will run from March into December, will see the milling and resurfacing of five miles of State Route 376 between Interstate 79 and the Fort Pitt Tunnel. In addition, there will be related bridge work, drainage improvements, guiderail upgrades, better signage and pavement marking and concrete barrier replacement.

Six full weekend closures are expected throughout the year, but none will take place during the Andrew Carnegie Free Library's Civil War Day on April 11 or the borough's annual 5K race April 25.

There will also be 70 overnight closures from 10 p.m. till 6 a.m. in alternating directions. Forty will be outbound and 30 will be inbound. Cars will be detoured.

Advertise with us

Mayor Jack Kobistek said Carnegie's business owners are concerned that these closures may hurt sales. However, the mayor was more worried that the increased deceleration lane into Carnegie and the acceleration lane towards town may back up.

PennDOT’s first full closure for Parkway repaving, slated for between Interstate 79 and the Green Tree exit, is scheduled for the April 18 weekend, weather permitting. The schedule for the second closure is not known yet. However, during these closures all of the Parkway traffic will be detoured through Carnegie, with officers stationed at key intersections to help traffic move through the town.

In a related matter, Greentree Road is scheduled for repaving in early April. However, most of the work will take place overnight and lane restrictions rather than full closures are planned.

Carole Gilbert Brown, freelance writer: post-gazette.com.