A weekend of full closures on the Parkway West will be followed by a temporary return to normality.

The Pennsylvania Department of Transportation announced Thursday that the parkway will be closed outbound from 2 a.m. to 4 p.m. Saturday from Green Tree to Interstate 79, with single-lane traffic inbound during the same hours.

The inbound parkway will close from 10 p.m. Saturday to 2 p.m. Sunday from I-79 to Green Tree, with single-lane traffic outbound.

Long delays are likely, and PennDOT is urging drivers to use alternate routes.

Advertise with us

Over the weekend, crews will pave, remove barriers and paint lines. When the work is complete, the $72.8 million parkway reconstruction project will go on winter hiatus. The on- and off-ramps at Carnegie will reopen, temporary barriers will be removed, and parkway lanes will be restored to their normal 12-foot width.

Motorists have been dealing with narrow lanes, concrete barriers, lane closures and detours since the project began Aug. 25 in the area of the Carnegie interchange. PennDOT started a series of overnight closures in early October when it determined that it was unsafe to move traffic through the work zone in a single-lane pattern.

Construction will resume in early March, PennDOT said. The project calls for reconstructing the parkway from I-79 to the Fort Pitt Tunnels, including repaving, reconstruction of shoulders, replacement of the center barrier, improvements to bridges, minor lengthening of some interchange ramps and new signs.

The outbound detour for this weekend is as follows: Exit at Green Tree/​Crafton (Exit 67), left on Route 121 toward Crafton; left on Mansfield Avenue; left on Noblestown Road-Route 50 to East Main Street; right on Jane Street to Mansfield Boulevard and West Main Street to the I-79 ramp; north on I-79 to the parkway.

The inbound posted detour exits at I-79 (Exit 64A); travels south to Carnegie (Exit 57); left on West Main Street to Mansfield Boulevard; right on Chestnut Street; left on East Main Street to Noblestown Road; right on Mansfield Avenue; left on Greentree Road; right on Parkway Center Drive to the parkway on-ramp.

The Fort Pitt Tunnels, site of a separate $14.2 million project to remove the ceilings, will be open this weekend and next, PennDOT spokesman Steve Cowan said. The next weekend closure will occur in December, but the schedule has not been made final.