Construction on the new Peters Township High School is running a bit behind, but according to the district’s construction management firm, there’s nothing to worry about.

Teachers and students will have a new place for learning for the 2020-21 school year.

“We are still tracking a little bit behind,” said Roshelle Fennell, of Reynolds Construction, at a Nov. 18 school board meeting.

But, she added, “At this point, we’re not really worried about it yet.” She said she’s confident that the academic areas will be finished on time.

Advertise with us

One issue the project — being built off East McMurray Road — is having is a shortage of masonry workers.

Ms. Fennell said she has met with Nello Construction, of Carnegie, one of the contractors on the project, about adding more masonry crews and coming up with a recovery schedule.

Ms. Fennell also updated the board on the progress of the school.

The academic zone is closed in for the winter, and temporary heating has been installed to allow for drywall finishing and the installation of rough-ins for plumbing and electrical service.

In the auditorium, crews are prepping to pour the floor, which Ms. Fennell said should be done by the end of the year.

Advertise with us

The running track has been installed around the main gymnasium, and the floor of the main gym is set to be poured soon.

Outside the school, the permanent water line and permanent electrical transformer have been installed and crews are finishing up the grading in the parking lot.

The board approved a few change orders on the project including $88,670 to Reynolds Construction for commissioning services.

Board member Ronald Dunleavy said Reynolds will go through the building and validate all of the mechanical systems to make sure they function correctly.

Additionally, the board approved a $35,445 change order from Nello Construction to change the tile in one stairway from vinyl terrazzo and approved a $4,363 change order from The Farfield Co., of Lilitz, to provide fiber-optic cabling for the natatorium scoreboard.

Advertise with us

In other business, the board approved a resolution stipulating taxes for the 2020-21 school year will not be increased by more than the district’s Act 1 index, which is 2.4%.

For taxpayers, that means the millage rate cannot go up by more than 0.324 mills, or about $32 for every $100,000 of assessed property value.

The district’s 2019-20 tax rate is 13.5 mills, or about $1,350 on every $100,000 of assessed value.