The construction project at Chartiers Valley Middle School is running behind schedule, but the delay is not expected to affect the completion date for the work and students are still scheduled to occupy new classrooms by the start of the 2017-18 school year.
Mucci Construction, the district’s general contractor, has established a recovery schedule to make up for the delay, including working on Saturdays and working extended hours during the week, superintendent Brian White said at the Jan. 24 school board meeting.
A mechanical room at the middle school fell behind schedule, and Mr. White said Mucci had informed the district about the delay.
Board president Tony Mazzarini said the board will look over the contractor’s recovery schedule and progress over the next couple of weeks.
According to a monthly report from the district’s construction management firm, P.J. Dick, the district has paid $78.6 million of the estimated $92.4 million cost for construction and renovation at the middle school and high school. A groundbreaking for the project was held at the end of May.
At last week’s meeting, parent Beth Eckenrode asked the school board for greater transparency concerning the project.
In other business, Mr. White announced that high school history teacher Bob Rodrigues is a finalist for the 2017 Consortium for Public Education’s Champions of Learning Award in the teaching category. The winner will be announced in April.
Deana Carpenter, freelance writer: suburbanliving@post-gazette.com.




Comments
Welcome to Post-Gazette subscriber-only commenting community. Please review our community guidelines.